TaiLexi AI U.S. Case Law

TM Partridge Lumber Co. v. Michigan Cent. R. Co.

T. M. Partridge Lumber Co. v. Michigan Cent. R. Co.

TM Partridge Lumber Co. v. Mich. Cent. R. Co., 26 F.2d 615 (8th Cir. 1928)
Download
Format
Include

Star paging (*137) is kept for pin cites.

Court
Court of Appeals for the Eighth Circuit · U.S. Courts of Appeals
Decided
May 16, 1928
Docket
No. 7656
Judges
Van Valkenburgh, Reeves, Otis
Citations
26 F.2d 6151928 U.S. App. LEXIS 3750

Opinion of the Court — Otis

OTIS, District Judge.

On April 18, 1922, the plaintiff in error, defendant below and hereinafter referred to as the defendant, shipped a ear of cedar poles from St. Boniface, Manitoba, to itself at Pinconning, Mich. Later the shipment was reeonsigned, and on or about May 16, 1922, delivered to the Detroit Edison Company at Detroit. Defendant should have paid defendant in error, plaintiff below and hereinafter referred to as plaintiff, $345.63 as freight charges. It did pay $386.50, or $40.87 more than was justly due. It claimed a refund, and was erroneously refunded $60.21 more than the amount to which it was entitled. On September 8, 1924, to partially reimburse plaintiff for this overpayment, defendant paid plaintiff $4.46, leaving still unpaid of the overpayment the amount of $55.75. Plaintiff brought this suit February 19,1926, and had judgment below for that amount.

It is one of the contentions of defendant that, if this is an action to recover freight charges, then the statute of limitations had run before the action was begun. The statute reads:

“All actions at law by carriers subject to this act for recovery of their charges, or any part thereof, shall be begun within three years from the time the cause of action accrues, and not after.” 41 Stat. 492 ; Comp. Stat. § 8584 (49 USCA § 16 (3), (a).

But that'this is not an action for the recovery of charges is too clear for argument) and the trial court properly so held. Therefore this statute has no application. The trial court held, we'.think properly, that the action is one on implied contract to refund money paid through error. If so, however, it is not a suit or proceeding arising under any law regulating commerce, or within any other class of suits of which the federal District Courts have original jurisdiction. For that reason it should have been dismissed by the trial court. Section 37, Judicial Code (28 USCA § 80).

Reversed, with directions to dismiss at plaintiff’s costs.

Concurrence — Van Valkenburgh

VAN VALKENBURGH, Circuit Judge

(concurring). I concur in the disposition of the case directed in the foregoing opinion. If the action be viewed as one on implied contract to refund money paid through mistake, the court below was without jurisdiction. If, as I think, it is for the recovery of carriers’ charges, it is barred by limitation.

From the correspondence between the parties and their representatives set out in the record, it appears that plaintiff in error on June 30, 1922, made claim for overcharge in the sum of $130.84. July 25, 1922, defendant in error acknowledged a claim for $75.92. October 26, 1922, the railroad asked the lumber company to reduce the claim to $85.48. February 15, 1923, it advised plaintiff in error that “if you will amend yourx claim to $101.08,. we will be pleased to place in line for payment.” Amendment and payment followed. August 13, 1924, the accounting department of the railroad notified the lumber company that in this refund there had been an overpayment of $4.46. The lumber company remitted that amount to the railroad. June 17, 1925, the accounting department again revised its figures and made demand for an additional sum of $55.75 because of alleged overpayment in its refund of $101.08.

.Upon refusal to meet this demand this action was filed February 17, 1926. In the stipulation of facts it is agreed: “That the balance of the overpayment by the plaintiff to the defendant still unpaid is fifty-five dollars seventy-five cents ($55.75).”

Paragraph 3 of section 16 of the Interstate Commerce Act, as amended June 7, 1924, provides that: “The cause of action in respect of a shipment of property shall, for the purposes of this section, be deemed to accrue upon delivery or tender of delivery thereof by the carrier, and not after.” 49 USCA § 16 (3), (e); Comp. St. § 8584 (3), (e).

This action is in effect one for the recovery of a part of the carrier’s charge; other *617 wise, the ultimate result of the transaction is a rebate of $55.75 to this shipper. But the delivery was made May 16, 1922; consequently, by the unambiguous terms of the statute, this action is barred. Without reflection upon the parties to this controversy, it is obvious that such vacillating methods of accounting may be made the means of granting rebates and concessions under specious forms of procedure. The remedy, however, lies with Congress. The courts must administer the law as it is written.

Combined text as published — syllabus, headnotes and all opinions in one document

26 F.2d 615 (1928)

T. M. PARTRIDGE LUMBER CO.

v.

MICHIGAN CENT. R. CO.

No. 7656.

Circuit Court of Appeals, Eighth Circuit.

May 16, 1928.

*616 Stanley B. Houck, of Minneapolis, Minn., for plaintiff in error.

Allan Briggs and Briggs, Weyl & Briggs, all of St. Paul, Minn., for defendant in error.

Before VAN VALKENBURGH, Circuit Judge, and REEVES and OTIS, District Judges.

OTIS, District Judge.

On April 18, 1922, the plaintiff in error, defendant below and hereinafter referred to as the defendant, shipped a car of cedar poles from St. Boniface, Manitoba, to itself at Pinconning, Mich. Later the shipment was reconsigned, and on or about May 16, 1922, delivered to the Detroit Edison Company at Detroit. Defendant should have paid defendant in error, plaintiff below and hereinafter referred to as plaintiff, $345.63 as freight charges. It did pay $386.50, or $40.87 more than was justly due. It claimed a refund, and was erroneously refunded $60.21 more than the amount to which it was entitled. On September 8, 1924, to partially reimburse plaintiff for this overpayment, defendant paid plaintiff $4.46, leaving still unpaid of the overpayment the amount of $55.75. Plaintiff brought this suit February 19, 1926, and had judgment below for that amount.

It is one of the contentions of defendant that, if this is an action to recover freight charges, then the statute of limitations had run before the action was begun. The statute reads:

"All actions at law by carriers subject to this act for recovery of their charges, or any part thereof, shall be begun within three years from the time the cause of action accrues, and not after." 41 Stat. 492 ; Comp. Stat. § 8584 (49 USCA § 16 (3), (a).

But that this is not an action for the recovery of charges is too clear for argument, and the trial court properly so held. Therefore this statute has no application. The trial court held, we think properly, that the action is one on implied contract to refund money paid through error. If so, however, it is not a suit or proceeding arising under any law regulating commerce, or within any other class of suits of which the federal District Courts have original jurisdiction. For that reason it should have been dismissed by the trial court. Section 37, Judicial Code (28 USCA § 80).

Reversed, with directions to dismiss at plaintiff's costs.

VAN VALKENBURGH, Circuit Judge (concurring).

I concur in the disposition of the case directed in the foregoing opinion. If the action be viewed as one on implied contract to refund money paid through mistake, the court below was without jurisdiction. If, as I think, it is for the recovery of carriers' charges, it is barred by limitation.

From the correspondence between the parties and their representatives set out in the record, it appears that plaintiff in error on June 30, 1922, made claim for overcharge in the sum of $130.84. July 25, 1922, defendant in error acknowledged a claim for $75.92. October 26, 1922, the railroad asked the lumber company to reduce the claim to $85.48. February 15, 1923, it advised plaintiff in error that "if you will amend your claim to $101.08, we will be pleased to place in line for payment." Amendment and payment followed. August 13, 1924, the accounting department of the railroad notified the lumber company that in this refund there had been an overpayment of $4.46. The lumber company remitted that amount to the railroad. June 17, 1925, the accounting department again revised its figures and made demand for an additional sum of $55.75 because of alleged overpayment in its refund of $101.08.

Upon refusal to meet this demand this action was filed February 17, 1926. In the stipulation of facts it is agreed: "That the balance of the overpayment by the plaintiff to the defendant still unpaid is fifty-five dollars seventy-five cents ($55.75)."

Paragraph 3 of section 16 of the Interstate Commerce Act, as amended June 7, 1924, provides that: "The cause of action in respect of a shipment of property shall, for the purposes of this section, be deemed to accrue upon delivery or tender of delivery thereof by the carrier, and not after." 49 USCA § 16 (3), (e); Comp. St. § 8584 (3), (e).

This action is in effect one for the recovery of a part of the carrier's charge; otherwise, *617 the ultimate result of the transaction is a rebate of $55.75 to this shipper. But the delivery was made May 16, 1922; consequently, by the unambiguous terms of the statute, this action is barred. Without reflection upon the parties to this controversy, it is obvious that such vacillating methods of accounting may be made the means of granting rebates and concessions under specious forms of procedure. The remedy, however, lies with Congress. The courts must administer the law as it is written.

How later courts describe this case

No later court has written an explanatory parenthetical about this case yet.

1940: 11942: 21955: 11956: 11958: 11968: 11977: 12026: 119402026peak 1942 · 2

Most recent

  1. Linna Chea v. Lite Star ESOP CommitteeNo. 1:23-cv-00647 (E.D. Cal. Feb. 11, 2026)
  2. The Atchison, Topeka and Santa Fe Railway Company v. M. E. Belt and Hazel Belt, D/B/A Belt Fur and Wool Company549 F.2d 1196 (8th Cir. 1977)
  3. Eickhof Construction Co. v. Great Northern Railway Co.291 F. Supp. 44 (D. Minnesota 1968)
  4. St. Louis-San Francisco Railway Co. v. Willard Mirror Co.160 F. Supp. 895 (W.D. Ark. 1958)
  5. Thompson v. Milwhite Co.292 S.W.2d 148 (Tex. App. 1956)
  6. Sanantex Oil Co. v. Thompson280 S.W.2d 252 (Tex. App. 1955)

Citing references are not a citator: they show that a later opinion cites this case, not whether it followed, distinguished, or overruled it. Check negative history before relying on this case.

Authorities cited 0

No citations to other opinions in this database were found.

Keyboard shortcuts

/Focus the search box
j kNext / previous result
EnterOpen the selected result
xAdd / remove the selected result from the download list
n pNext / previous search term in a case
cCopy the citation of the current case
+ −Larger / smaller reading text
?Show this list