S. Birch & Sons Construction Co. v. City of Fargo

S. BIRCH & SONS CONSTRUCTION COMPANY, a Corporation, Appellant, v. CITY OF FARGO, a Municipal Corporation, Et Al., Respondents

S. Birch & Sons Constr. Co. v. City of Fargo, 167 N.W. 390 (N.D. 1918)
Download
Format
Include

Star paging (*137) is kept for pin cites.

Court
North Dakota Supreme Court · State Highest Courts
Decided
April 10, 1918
Judges
Robinson
Citations
167 N.W. 39039 N.D. 3701918 N.D. LEXIS 36
Disposition
Affirmed.
Headnotes
City commissioners — contract for paving — payment of price — mandamus to compel — duty of commissioners — specific performance of — mandamus will only lie for’ — pleading — demurrer. This is a suit for a mandamus to compel the city commissioners to pay on the contract price of a pavement a balance of 15 per cent which has been retained pursuant to the paving contract. However, under the plain words of the statute the writ of mandamus may be issued to the city commissioners only “to compel a specific performance of an act wliicli the law specifically enjoins as a duty resulting from an office, trust, or station.” Manifestly there is no claim that the city commissioners have neglected the performance of a duty which the law specifically enjoins on them. Hence, the order sustaining the demurrer is affirmed.
Summary
Appeal from an order of the District Court of Cass County, Honorable A. T. Cole, Judge. Plaintiff appeals.

Syllabus and headnotes are prepared by the reporter or publisher, not the court, and are not part of the opinion.

Opinion of the Court — Robinson

Robinson, J.

This is an appeal from an order sustaining a demurrer to the complaint. As it shows plaintiff made a paving contract with the city of Fargo, and did paving on which he received 85 per cent of the contract' price, amounting to $102,300. The balance 15 per cent, $17,999.18, remains unpaid. The contract provides as follows: “Monthly estimates will be given by the engineer of value of work actually constructed and in its permanent place, and certificates for 85 per cent of estimated value of the work done will be issued, the remaining 15 per cent to be reserved until the completion of the whole work.” Under the contract work may be suspended by the engineer, and he has directed the suspension of all work on First avenue foy the reason that the recent construction of a sewer has made the avenue unfit for paving until the ground settles, which may not be until the middle of next summer.

The plaintiff has duly completed all the work except the pavement on First avenue, and has requested the city commissioners to pay the 15 per cent retained. This they have failed to do because they doubt the right and legal authority to do it. There is no -showing that the commissioners have ever passed a resolution to take any official action in regard to the pavement, and by their city attorney they have appeared and opposed the motion for a mandamus. The demand of the complaint is that a peremptory writ issue directing the city commissioners to issue to Birch & Sons warrants on the paving district for the unpaid 15 per cent, amounting to $17,999.18. The contract in regard to the manner of making payments accords with the statutes in Comp. Laws *372 1913, § 3710. “In case the contractor to whom any such contract shall bo let shall properly perform the work therein designated, the city council may, from time to time in its discretion, as the work progresses, pay to such contractor upon an estimate made by the city engineer of the amount already earned thereunder, 85 per cent of the amount shown by such estimate to have been so earned, in warrants drawn on the fund from which the same is to be paid.”

Thus it appears that the city has justly complied with its written contract, and the plaintiff has no cause of action against it, but it is urged that the enforced delay in completing the work is a damage to the plaintiffs, and that the city commissioners are quite willing to pay the 15 per cent if this court would only issue a mandamus directing them to do it, and clearly indicated that it is right and proper for them to make such payment.

However, under the plain words of the statute the writ of mandamus may be issued to the city commissioners only “to compel a specific performance of an act which the law specifically enjoins as a duty resulting from an office, trust, or station.” Comp. Laws, § 8457.

Manifestly there is no claim that the city commissioners have neglected the performance of a duty which the law specifically enjoins on them. Hence, the order sustaining the demurrer must be affirmed.

How later courts describe this case

No later court has written an explanatory parenthetical about this case yet.

1937: 119372026peak 1937 · 1

Relies on it most ⓘ

  1. Federal Land Bank v. Johnson274 N.W. 668 (N.D. 1937)

Most recent

  1. Federal Land Bank v. Johnson274 N.W. 668 (N.D. 1937)

Citing references are not a citator: they show that a later opinion cites this case, not whether it followed, distinguished, or overruled it. Check negative history before relying on this case.

Authorities cited 0

No citations to other opinions in this database were found.

Keyboard shortcuts

/Focus the search box
j kNext / previous result
EnterOpen the selected result
xAdd / remove the selected result from the download list
n pNext / previous search term in a case
cCopy the citation of the current case
+ −Larger / smaller reading text
?Show this list