Syllabus
Contract for Sale of Vruit—Construction—Partial Delivery—Time of Payment.—The defendant agreed to take and pay for all the fruit raised by the plaintiff at a uniform rate per pound for all fruit raised and delivered at the works of the defendant. As the fruit ripened the plaintiff delivered and the defendant received it under the contract; but the latter refused to pay for the fruit until all was delivered; and thereupon the plaintiff declined to deliver any more, and sued for the value of that delivered. Held, that according to the true construction of the contract, as each lot was ■ delivered and accepted by the defendant, there became due and payable from it to the plaintiff the value thereof at the rate per pound fixed in the contract.
Summary
Appeal from a judgment for the plaintiff in the Superior Court of El Dorado County.

Syllabus and headnotes are prepared by the reporter or publisher, not the court, and are not part of the opinion.

Opinion of the Court — Ross

Text extracted by OCR from a scanned original; check the original for exact wording.

Ross, J.:

The parties to this suit contracted with each other in writing as follows: “ The said company engage to take and pay for all the fruit raised by the said Francis Yeerkamp at the uniform rate of five eighths (-§) of a cent per pound for all fruit raised and delivered at the works of the above company, in Upper Placerville (excepting Mission grapes), and to furnish boxes for picking and hauling the fruit. The said Francis Yeerkamp, on his part, engages to deliver the fruit in good condition, and when in suitable ripeness, and will sell no fruit to other parties, excepting one load early.”

The parties could not very well have made their contract more indefinite. The fruit referred to in the written agreement was such as was then growing on land of the plaintiff. As the fruit ripened, the plaintiff delivered and the defendant received it under the contract. After a part had been thus delivered and accepted, the plaintiff demanded of defendant payment for that delivered at the agreed rate, but the defendant refused to make such payment until the plaintiff should first deliver all of the fruit referred to. Thereupon plaintiff declined to deliver to defendant any more, and sued for the value of that delivered and accepted. The defendant resists the.action on the ground that the delivery of all the fruit referred to in the contract was a condition precedent to the payment for any. We do not think that the proper construction of the agreement between the parties. The contract must be construed with reference to the subject-matter of it. It was *231 executory in its nature. It could not be known in advance how much of any particular kind of fruit there would be. In the nature of things it ripened at different times, and had to be delivered at different times. The contract fixed the rate per pound at which the defendant was to pay for it, and, in our opinion, according to its true construction, as each lot was delivered to and accepted by defendant there became due and payable from it to the plaintiff the value thereof at the rate per pound fixed in the contract.

Judgment affirmed.

McKinstry, J., and McKee, J., concurred.

How later courts describe this case

No later court has written an explanatory parenthetical about this case yet.

1904: 11909: 11910: 11920: 11922: 11923: 119042026peak 1904 · 1

Relies on it most ⓘ

  1. L.A. Gas & Elec. Co. v. Amalgamated Oil Co.106 P. 55 (Cal. 1909)
  2. Dees v. Self Bros.51 So. 735 (Ala. 1910)
  3. United Canneries Co. v. Seelye292 P. 341 (Cal. Ct. App. 1920)
  4. Romer v. Wehner214 P. 993 (Cal. Ct. App. 1923)
  5. Matthews Glass Co. v. Burk70 N.E. 371 (Ind. 1904)
  6. Helms v. Pacific Mill Timber Co.207 P. 708 (Cal. Ct. App. 1922)

Most recent

  1. Romer v. Wehner214 P. 993 (Cal. Ct. App. 1923)
  2. Helms v. Pacific Mill Timber Co.207 P. 708 (Cal. Ct. App. 1922)
  3. United Canneries Co. v. Seelye292 P. 341 (Cal. Ct. App. 1920)
  4. Dees v. Self Bros.51 So. 735 (Ala. 1910)
  5. L.A. Gas & Elec. Co. v. Amalgamated Oil Co.106 P. 55 (Cal. 1909)
  6. Matthews Glass Co. v. Burk70 N.E. 371 (Ind. 1904)

Citing references are not a citator: they show that a later opinion cites this case, not whether it followed, distinguished, or overruled it. Check negative history before relying on this case.

Authorities cited 0

No citations to other opinions in this database were found.

Keyboard shortcuts

/Focus the search box
j kNext / previous result
EnterOpen the selected result
xAdd / remove the selected result from the download list
n pNext / previous search term in a case
cCopy the citation of the current case
+ −Larger / smaller reading text
?Show this list