Order, Supreme Court, New York County (Ira Gammerman, *332 J.H.O.), entered September 19, 2005, which granted plaintiffs motion for partial summary judgment, severed the remainder of the action, ordered that the action proceed to discovery and effectively denied defendant’s cross motion to dismiss the complaint, unanimously reversed, on the law, without costs, plaintiffs motion denied, defendant’s cross motion granted and the complaint dismissed. The Clerk is directed to enter judgment accordingly.
The parties’ agreement for plaintiff to supply defendant with towels was a standard City requirements contract containing a broad dispute resolution clause that mandated a three-step procedure prior to a claimant seeking limited judicial review of whether the administrative determination was in violation of lawful procedures, was affected by an error of law, or was arbitrary and capricious or an abuse of discretion. Upon rejection of, and nonpayment for, several shipments of its towels, plaintiff pursued the first two steps of the procedure, bringing the dispute before the agency head of the Department of Citywide Administrative Services and then the City Comptroller, who each found against plaintiff. Instead of submitting the dispute to the Contract Dispute Resolution Board for the third-step review, plaintiff commenced this plenary action.
The complaint should have been dismissed because plaintiff failed to comply fully with the contractual dispute resolution procedure. In an effort to evade this requirement, plaintiff proffers interpretations of individual provisions of the procedure that are inconsistent with its plain intent and violative of basic principles of contractual construction. “[A] court should not ‘adopt an interpretation’ which will operate to leave a ‘provision of a contract . . . without force and effect’ ” (Corhill Corp. v S.D. Plants, Inc., 9 NY2d 595, 599 [1961]). “An interpretation that gives effect to all the terms of an agreement is preferable to one that ignores terms or accords them an unreasonable interpretation” (Ruttenberg v Davidge Data Sys. Corp., 215 AD2d 191, 196 [1995]). Concur—Tom, J.P., Mazzarelli, Williams, McGuire and Kavanagh, JJ.
How later courts describe this case
Explanatory parentheticals written by citing courts — 2 in all; the most informative distinct ones are shown.
-
(reversing summary judgment for the plaintiff and finding the case “should have been dismissed because [the] plaintiff failed to comply fully with the contractual dispute resolution procedure”)
-
(construing clauses providing for alternative dispute resolution mechanisms as mandatory is supported by the long-standing principle under New York law that contracts are to be interpreted in a manner that would give full effect to all provisions)
Cited by 16 cases
View all citing references →Relies on it most ⓘ
- Lamm v. State Street Bank & Trust Co.
- VCG Special Opportunities Master Fund Ltd. v. Citibank, N.A.
- Gessin Electrical Contractors, Inc. v. 95 Wall Associates, LLC
- ERC 16W Ltd. Partnership v. Xanadu Mezz Holdings LLC
- Stonebridge Capital, LLC v. Nomura International PLC
- Kafa Investments, LLC v. 2170-2178 Broadway, LLC
Most recent
- Stuver v. Greenlight Parent, L.P.
- Success Academy Charter Schs., Inc. v. Liberty Sq. Realty Corp.
- Hudson Neurosurgey, PLLC v. UMR, Inc.
- People Care Inc. v. City of N.Y. Human Resources Admin.
- People Care Inc. v. City of New York Human Resources Admin.
- Commodore Constr. Corp. v. Contract Dispute Resolution Bd. of the City of N.Y.
Citing references are not a citator: they show that a later opinion cites this case, not whether it followed, distinguished, or overruled it. Check negative history before relying on this case.