TaiLexi AI U.S. Case Law

Great Atlantic & Pacific Tea Co. v. Rust Engineering Co.

Great Atlantic & Pacific Tea Company, Inc. v. Rust Engineering Company

Great Atl. & Pac. Tea Co. v. Rust Eng'g Co., 75 Misc. 2d 920 (N.Y. Sup. Ct. 1973)
Download
Format
Include

Star paging (*137) is kept for pin cites.

Court
New York Supreme Court · State Trial Courts
Decided
August 1, 1973
Judges
Yesawich
Citations
75 Misc. 2d 920349 N.Y.S.2d 2431973 N.Y. Misc. LEXIS 1335

Opinion of the Court — Yesawich

Text extracted by OCR from a scanned original; check the original for exact wording.

Paul J. Yesawich, Jr., J.

This is a suit by the owner of a recently constructed food processing plant against the general contractor, the roofing subcontractor and the manufacturer and supplier of roofing material and its surety. The manufacturer and supplier, defendant GAF Corporation, moves to dismiss so much of plaintiff’s fourth cause of action as is based on breach of warranty on the ground that it was not commenced within four years after the cause of action accrued pursuant to igection 2-725 of the Uniform Commercial Code.

*921 Plaintiff’s specifications called for a 20-year bonded or guaranteed roof. Pursuant to an August 18,1964 purchase order which had been submitted to the Buberoid Company (GAF’s predecessor), GAF delivered roofing materials and supplies to the roofing subcontractor at the plant site in Horseheads, New York. Work on the roof commenced in 1964. The last delivery by GAF was apparently made on or about July 2,1965. In 1967 leaks appeared in the roof. Defendant GAF made certain repairs, but in 1969 determined that the leaks were due to causes other than the natural elements, and declined to make further repairs. The action herein was instituted in March of 1971.

The moving defendant argues that the warranty cause of action accrued after September 27,1964, the effective date of the Uniform Commercial Code and therefore the suit is time barred for it is subject to the Uniform Commercial Code’s four-year Statute of Limitations. However, the operative date for determining whether the Uniform Commercial Code or precode law applies is the date when the transaction was entered into.

(Uniform Commercial Code, § 10-102, subd. [2].) Since here the transaction was entered into before the date when the Uniform Commercial Code became effective in this State (Uniform Commercial Code, § 10-105), the preoode six-year period of limitation applies (CPLR 213, subd. 2), and inasmuch as the transaction was not completed until July 2, 1965, the last date when delivery was made, this action is riot time-barred. (Mendel v. Pittsburgh Plate Glass Co., 25 N Y 2d 340; Lewis v. Royle & Sons, 37 A D 2d 639; Kakargo v. Grange Silo Co., 11 A D 2d 796.)

Motion denied, submit order.

How later courts describe this case

No later court has written an explanatory parenthetical about this case yet.

1978: 11979: 11980: 119782026peak 1978 · 1

Relies on it most ⓘ

  1. A. J. Aberman, Inc. v. Funk Building Corp.420 A.2d 594 (Pa. Super. Ct. 1980)
  2. Johnson v. American Mutual Liability Insurance368 So. 2d 506 (Ala. 1978)
  3. Bulova Watch Co. v. Celotex Corp.389 N.E.2d 130 (N.Y. 1979)

Most recent

  1. A. J. Aberman, Inc. v. Funk Building Corp.420 A.2d 594 (Pa. Super. Ct. 1980)
  2. Bulova Watch Co. v. Celotex Corp.389 N.E.2d 130 (N.Y. 1979)
  3. Johnson v. American Mutual Liability Insurance368 So. 2d 506 (Ala. 1978)

Citing references are not a citator: they show that a later opinion cites this case, not whether it followed, distinguished, or overruled it. Check negative history before relying on this case.

Authorities cited 0

No citations to other opinions in this database were found.

Keyboard shortcuts

/Focus the search box
j kNext / previous result
EnterOpen the selected result
xAdd / remove the selected result from the download list
n pNext / previous search term in a case
cCopy the citation of the current case
+ −Larger / smaller reading text
?Show this list