TaiLexi AI U.S. Case Law

Smith v. Norris

James F. Smith v. Benjamin P. Norris

Smith v. Norris, 120 Mass. 58 (1876)
Download
Format
Include

Star paging (*137) is kept for pin cites.

Court
Massachusetts Supreme Judicial Court · State Highest Courts
Decided
March 6, 1876
Judges
Devens
Citations
120 Mass. 581876 Mass. LEXIS 113
Headnotes
A., the owner of a lot of land, made a contract with B., whereby A. was to advance money to B. to build houses on the land, and to convey the land to B. for a certain sum and the amount of advances; and B. was to build the houses and buy the land. B. made a contract with C. to do certain work on the houses for an entire sum. Before 0. completed the work. B. went into bankruptcy, and C. afterwards in good faith went on and did some work on one of the houses under the contract, but did not complete his work owing to the failure of B. to comply with the terms of the contract. Held, that C. was entitled to a lien under the Gen. Sts. c. 150, for the value of his labor. tt the St. of 1872, c. 318, § 2, applies to the case of labor performed under an entire contract, the work called for by the contract not being wholly performed, owing to the failure of the other party to the contract to perform his part, it is no objection to the enforcement of a lien under the statute, that the petitioner, in his statement of a lien, has stated the value of his labor to he greater than it actually was, it not appearing that the petitioner had wilfully and knowingly claimed more than was due.
Summary
Petition by James F. Smith and John H. Le Cain to enforce a mechanic’s lien under the Gen. Sts. c. 150, for work done upon a block of five houses on Dennis Street in Boston. The certificate, filed by the petitioners in the office of the city clerk on March 7, 1873, set forth that the petitioners had a claim against William Eadie and Theodore G. Brown, late co-partners under the firm name of Eadie & Brown, amounting to $400, according to an account annexed and made part of the certificate. The first item of this account, under, date of February 6, 1873, was : “ For 247§ days’ labor on five houses on Dennis Street, in Boston, $1050.” The other items were various credits, made in 1872, amounting to $650, leaving a balance of $400. The certificate then set forth that the claim was made for and on account of labor performed and furnished in the erection of five brick houses on land owned by Benjamin P. Norris, and situate on Dennis Street in Boston, and described their situation on the street; that the houses constituted one block; that the labor was performed and furnished in and upon said houses by virtue of a contract entered into on September 24, 1872, between the petitioners of the one part and Eadie & Brown of the other part, a copy of the contract being annexed and made part of the certificate; * that the petitioners had performed and furnished labor under the contract upon said houses to the value of $1050, and had received the sum of $650, leaving a balance due of $400; that the completion of the work was stopped without any fault on the petitioners’ part; and that they ceased laboring upon said houses on February 6, 1873. The petition also set forth a claim for extra work done on said houses in accordance, with directions given from time to time by Eadie & Brown, amounting to $65, after deducting all just credits; and claimed a lien upon said houses and the land under them. The case was sent to an auditor, who found that the respondent was the owner of the land described in the petition; that on August 20, 1872, he and Eadie & Brown «made and signed the following contract under seal: “ Agreement of sale made and concluded this twentieth day of August, A. D. 1872, by and between Benjamin P. Morris, of Boston, in the county of Suffolk, of the first part, and William Eadie and Theodore G. Brown, both of said Boston, of the seoond part, witnesseth, that the said Morris agrees to sell and convey, and said Eadie & Brown agree to purchase, a certain parcel of land situated on the northwesterly side of Dennis Street in said Boston.” Then followed a description of the land. “ Said Eadie & Brown agree to pay for said land at the rate of one dol lar per square foot, being sixty-eight hundred and four dollars in all, and interest as hereinafter stated. Said Eadie & Brown are to commence immediately to erect on said land five two-story and French roof brick dwelling houses, each measuring at least seventeen feet front by thirty-seven feet deep, with two-story bay windows, and each house containing ten rooms and cellar, and being fitted for two families, with separate gas-pipes for each family, to be finished in good style, and each house to cost not less than thirty-five hundred dollars above the land. And said Morris is to advance to an amount not exceeding two thousand dollars in money and materials for the building of each of the said houses, at such times and in such amounts as he shall deem safe and expedient, reference being had to the progress of the said buildings. Deed or deeds of said premises free from all incumbrances, shall be given within seven months from this date by said Morris, provided always said Eadie Sc Brown shall, within said period, pay to said Morris all of said purchase money, together with taxes and interest thereon from this date at the rate of seven and T3T per centum per annum; and all moneys advanced by said Morris, together with interest thereon, at the rate of eighteen per centum per annum, from the respective times when such advances are made, and the value in money of all materials furnished by said Morris or procured by his order or indorsement, together with such interest or expenses on the same as the said Morris may be obliged to pay. But if said payments are not made within said period of seven months, thei this agreement is to be null and void.” Indorsed upon this contract was an assignment by the assignee in bankruptcy of Eadie & Brown, dated February 18, 1873, of all their rights in the contract to Isaac G. Caswell; and an agreement, dated February 21, 1873, signed by Norris, whereby he agreed to be bound, by all the covenants contained in the contract, to Caswell and one Weeks, as fully and completely as though the contract had been originally executed by them, and extending the contract to June 20, 1873. The auditor further found that on September 24,1872, Eadie & Brown, with the knowledge of the respondent, entered into the contract with the petitioners, as alleged in their petition; that the petitioners, with the knowledge and consent of the respondent, proceeded to build the houses as required by the contract ; that most of the carpenter’s work necessary to be done, before the houses were plastered, was done before December 12, 1872, on which day Eadie & Brown filed a petition in bankruptcy; that the petitioners were prevented from completing their contract with Eadie & Brown, by the failure of the latter to furnish the materials, as required by the contract; that some work was done by the petitioners after December 12, 1872, on one only of the houses, which work Avas done in good faith, with the expectation that they were to go forAvard and finish the work under the contract; that the labor on the houses ceased on February 6, 1873 ; that five eighths of the entire work called for by the contract was performed by the petitioners at the time the labor ceased; that one or the other of the petitioners either had knowledge of the bankruptcy of Eadie & Brown prior to February 6, 1873, or had knowledge of such facts as should have put them on inquiry; that the value of this work was §937.50; and that the petitioners were entitled to receive therefor the sum of §287.50, being the amount remaining after deducting §650, the amount of money received. The auditor also found that the petitioners had done extra work, with the knowledge and consent of the respondent, to the amount of §65, for which they vere entitled to a lien; and that they were entitled to recover as compensation for the work done under the contract and for extra work the sum of §352.50. The Superior Court ordered judgment for the petitioners fof $357.79; and the respondent appealed to this court.

Syllabus and headnotes are prepared by the reporter or publisher, not the court, and are not part of the opinion.

Opinion of the Court — Devens

Text extracted by OCR from a scanned original; check the original for exact wording.

Devens, J.

The contract between Norris and Eadie & Brown was similar to that in Hilton v. Merrill, 106 Mass. 528 . It was one of the purposes of their agreement that Eadie & Brown should proceed to erect a block of houses upon the land which, on certain terms, Norris was to convey to them, and for this purpose Norris was to advance a specified amount of money. By implication he authorized Eadie & Brown to employ, either directly or through sub-contractors, the workmen necessary foi this object, and the labor thus employed was performed by i» tendment of the statute, with the consent of Norris.

*63 The petitioners, in making their contract and entering upon its performance, had a right to rely not only on the promise of Eadie & Brown, but also on their lien upon the property as security for the work which they might do under it. When, therefore, Eadie & Brown became bankrupt, even if they were no longer personally liable for what the petitioners might after-wards do under their contract, the petitioners could still go on, relying upon their lien on the property, and finish the work for which , they had contracted, if in so doing they acted in good faith and for the purpose of completing their contract. The labor thus done would be under the authority which it must be inferred Norris had given Eadie & Brown to employ workmen, and would be performed on his estate with his consent.

Nor are the petitioners to lose their lien because, acting in good faith, they have failed fully to complete all the labor they agreed to perform ; that which they have done has been under the contract, to which the respondent consented, and it is that consent which subjects his estate to the lien. If, by the failure of the workmen in such a case fully to perform, any injury should have been occasioned, or their labor should have been less valuable, there might be a deduction from the contract price by way of recoupment. No such question has, however, been here presented. It has been found that what the petitioners have done, since the bankruptcy of Eadie & Brown, they did in good faith, expecting to be able to finish their contract, and that they have failed because the necessary materials were not furnished. They are entitled, therefore, to judgment for the amount which the auditor has decided to be due, having filed the necessary certificate within thirty days after the completion of the labor which they were able to perform.

Assuming, but not deciding, that the St. of 1872, c. 318, was intended to apply to an entire contract like that in the case at bar, which was for work and labor only, the certificate filed was still sufficient to meet all the requisitions of § 2 of that statute. In addition to the statements required by the Gen. Sts, c. 150, § 5, it set forth the entire price for the entire contract, the number of days’ labor performed, and the value of the same. Even if the value as stated was more than that which has been found to be due, the St. of 1872 is but an extension of the Gen. Sts. c. 150 *64 and, as it does not appear “ that the person filing the certificate has wilfully and knowingly claimed more than is his due,” the inaccuracy in the statement does not “ invalidate the proceedings.” Gen. Sts. c. 150, § 6. This certificate having been filed within thirty days after the completion ;f the labor which the petitioners were able to perform, they are therefore entitled to judgment for the amount which the auditor has found to be due.

Judgment affirmed.

How later courts describe this case

No later court has written an explanatory parenthetical about this case yet.

Cited by 15 cases

View all citing references →
1883–1884: 21889–1890: 21891–1892: 41893–1894: 11895–1896: 11897–1898: 11907–1908: 21927–1928: 11955–1956: 118832026peak 1891 · 4

Relies on it most ⓘ

  1. McCue v. Whitwell30 N.E. 1134 (Mass. 1892)
  2. Hart v. Reid219 N.W. 692 (Mich. 1928)
  3. Brown v. Haddock85 N.E. 573 (Mass. 1908)
  4. Nichols v. Culver51 Conn. 177 (1883)
  5. Albrecht v. C. C. Foster Lumber Co.26 N.E. 157 (Ind. 1890)
  6. O'Leary v. Roe45 Mo. App. 567 (1891)

Most recent

  1. Valentine Lumber & Supply Co. v. Thibeault130 N.E.2d 868 (Mass. 1955)
  2. Hart v. Reid219 N.W. 692 (Mich. 1928)
  3. Brown v. Haddock85 N.E. 573 (Mass. 1908)
  4. Farrell v. B. F. Sturtevant Co.80 N.E. 469 (Mass. 1907)
  5. Courtemanche v. Blackstone Valley Street Railway Co.48 N.E. 937 (Mass. 1898)
  6. Justice v. Elwert43 P. 649 (Or. 1896)

Citing references are not a citator: they show that a later opinion cites this case, not whether it followed, distinguished, or overruled it. Check negative history before relying on this case.

Authorities cited 1

DepthCaseCited by
Hilton v. Merrill, 106 Mass. 528 (1871) 19

Keyboard shortcuts

/Focus the search box
j kNext / previous result
EnterOpen the selected result
xAdd / remove the selected result from the download list
n pNext / previous search term in a case
cCopy the citation of the current case
+ −Larger / smaller reading text
?Show this list