Multnomah County v. United States Fidelity & Guaranty Co.

Multnomah Cnty. v. United States Fid. & Guar. Co., 180 P. 104 (Or. 1919)
Download
Format
Include

Star paging (*137) is kept for pin cites.

Court
Oregon Supreme Court · State Highest Courts
Decided
April 22, 1919
Judges
Bean, Bennett, Johns, McBride
Citations
180 P. 10492 Or. 1461919 Ore. LEXIS 100
Disposition
Beversed.
Headnotes
Highways — Improvement—Contractor’s Bond — Construction. 1. "Where highway eontraetor’s "bond is executed under Section 6266, L. O. L., as to' public contractor’s bond, the statute should be read in and become a part of the bond. Courts — Buies of Decision — Stare Decisis. 2. Where law laid down by decision of the Supreme Court construing public eontraetor’s bond executed under Section 6266, L. O. L., has been in force and effect for more than a year, during which time many similar bonds have been written, the ease has become stare decisis. Highways — Improvement—Construction of Bond — “Labor.” 3. Highway contractor’s bond executed under Section 6266, L. O.L., and conditioned upon his making prompt payment to all “persons supplying him * * labor * * for any prosecution of the work,” held to include payment to owner of horses for services of horses in 'prosejution of the work; such services constituting “labor.” [As to who is within the meaning of statutes relating to laborer, workman or servant, see note to 32 Am. Bep. 264.]
Summary
From Multnomah.: George N. Davis, Judge. Department 2. On January 27, 1916, plaintiff filed its complaint against the defendants in the Circuit Court of Multnomah County, and after the necessary corporate allegations avers that about January 21,1915, the defendant, Pacific Bridge Company, entered into a written contract with the plaintiff, Multnomah County, for the improvement of that portion of the Columbia River Highway known as Section D, in accord with the plans and specifications therefor, in and by which the contractor agreed “to furnish all materials, tools and equipment and all labor necessary to complete the work.” The complaint alleges that pursuant to said contract “and in accordance with the laws of the State of Oregon” the defendant Pacific Bridge Company, as principal, and United States Fidelity & Guaranty Company, as. surety, executed to Multnomah County its certain penal bond, conditioned “that Pacific Bridge Company should promptly pay all laborers, mechanics, subcontractors and materialmen, and all persons who should supply such laborers, mechanics, subcontractors or materialmen with supplies or provisions for •carrying on such work”; that the'Pacific Bridge Company “entered upon the work of carrying out said contract and making said improvement in accordance therewith”; that it sublet a portion of said work to Thomas A. Sweeney or contracted with him to furnish teams and equipment to haul materials to be used and which were used in the work of carrying out said contract ; and that during the months of August, September, October and November of 1915, R. J. O’Neil, for whose use and benefit this action was brought, furnished and supplied Sweeney with certain horses, pursuant to an agreement with him that he should keep the horses “in a camp established by him on said improvement work, assume the cost of feed and hire drivers for the same, and pay in addition to the said R. J. O’Neil the reasonable value of the labor performed by said horses in the work of teaming or hauling said materiads for use in said improvement.” It is further alleged that “the reasonable value of the labor so furnished and supplied by said R. J. O’Neil by said horses was the sum of $315,” no part of which has been paid; that the full amount thereof is due and Owing to the said O’Neil, and that prior to the commencement of the action he made the necessary proofs and furnished the required affidavits which gave him the right of action. A copy of the bond and a copy of the contract between the Bridge Company and Multnomah County are attached to the complaint as exhibits and made a part thereof. The defendant filed a demurrer upon the ground: “That said complaint does not state facts sufficient to constitute a cause of suit or action against the defendants herein or either thereof.” On February 21, 1916,\the trial court sustained the demurrer and dismissed the action and rendered judgment against the plaintiff for costs, from which ruling the plaintiff appealed, claiming, that the court erred in sustaining the demurrer to the complaint, and that is the only question presented on the appeal.

Syllabus and headnotes are prepared by the reporter or publisher, not the court, and are not part of the opinion.

Opinion of the Court — Johns

Text extracted by OCR from a scanned original; check the original for exact wording.

JOHNS, J.

The action is founded upon Section 6266, Lord’s Oregon Laws, which provides as follows:

“Hereafter any person or persons, firm or corporation, entering into a- formal contract with the State of Oregon, or any municipality, county, or school district within said state, for the construction of any buildings, or the prosecution and completion of any work, or for repairs upon any building or work, shall be required before commencing such work, to execute the usual penal bond with good and sufficient sureties, with the additional obligations1 that such contractor *149 or contractors shall promptly make payments to all persons supplying him or them labor or materials for any prosecution of the work provided for in such contracts”; etc.

The statute was enacted in 1903 and is entitled:

“An act to protect subcontractors, materialmen and laborers furnishing material for doing work upon public buildings, structures, superstructures or other public works”: Laws 1903, p. 256.

1. Under the rule of construction, this statute should be read into and become a part of the bond.

In the case of Multnomah County v. United States Fidelity & Guaranty Co., 87 Or. 198 ( 170 Pac. 525 , L. R. A. 19180, 685), an action^ was brought by the county against the defendant, for and on behalf of L. H, McMahan, against the same defendants here for the use of a caterpillar engine which it is alleged that McMahan hired to Sweeney and for the use of which he agreed to pay $10 per day. There, as here, a general demurrer was filed to the complaint and sustained by the trial court upon the theory that the use of the caterpillar engine did not come within the terms of the bond. That ruling was reversed by a decision of this court, written on January 22, 1918, by Mr. Justice Bean.

2. The law of that case is vigorously attacked by respondent, but it has been in force and effect for more than one year, and it is a matter of common knowledge that in the ordinary course of business many such bonds have been written in that time and the decision must have been known and acted upon at the time of their execution, and that case should now be stare decisis.

The purpose of the act was to protect all persons supplying “labor or materials for any prosecution of *150 the work provided for in such contract” and there is much stronger reason for holding that the use of horses comes within the meaning of the word “labor”as.used in the act than the rental of a caterpillar engine employed on the work. A caterpillar engine is a machine; a horse is a domestic animal with some degree of intelligence.

The respondents have cited definitions from Words & Phrases and the New Standard Dictionary as to the meaning of the words “labor and material” and of the word “labor,” but Century Dictionary defines the word “labor” as “work done by a human being or an animal,” and Words & Phrases, Volume 5, page 3951, says:

“Within the meaning of a statute giving a lien to ‘laborers and for persons furnishing materials to. contractors or subcontractors’ labor done by a man’s team may be fairly regarded as labor done by him, no right arising to anyone out of its services except to him,” citing Chicago N. E. R. Co. v. Sturgis, 44 Mich. 538, 541 ( 7 N. W. 213, 214 ).

The opinion in that case says:

“But the labor done by a man’s team may be fairly regarded as labor done by him within the meaning of this statute.”

The same authority also cites the case of Hogan v. Cushing, 49 Wis. 169 ( 5 N. W. 490, 491 ), in which the syllabus says:

“The ‘labor and services’ for which Chapter 95 of 1877 gives a lien upon logs, are not merely the personal manual labor and services of the claimant, but include those performed by his teams and servants.”

3. If O’Neil in person or through his own employees had used his horses in the “prosecution of the work” there would be no question about his right to recover *151 for the joint services of both horses and men. On legal principle, the same rule should apply where he hired out his horses to another to be used and they were so used. We hold that the word “labor” within the meaning of the act should be construed to include the services which the horses performed in the “prosecution of the work.”

Judgment is reversed. Reversed.

McBride, O. J., and Bean and Bennett, JJ., concur.

How later courts describe this case

No later court has written an explanatory parenthetical about this case yet.

Cited by 14 cases

View all citing references →
1919: 11920: 11923: 11925: 11926: 21927: 11928: 21933: 21935: 11940: 11970: 119192026peak 1926 · 2

Relies on it most ⓘ

  1. Franzen v. Southern Surety Co.246 P. 30 (Wyo. 1926)
  2. Payseno v. Padgett Co.212 N.W. 836 (N.D. 1927)
  3. Fulghum & Union Indemnity Co. v. State109 So. 644 (Fla. 1926)
  4. Union Indemnity Co. v. State ex rel. R. S. Armstrong & Bro.118 So. 148 (Ala. 1928)
  5. Universal Electric Const. Co. of Alabama v. Robbins194 So. 194 (Ala. 1940)
  6. Portland v. O'Neill192 P. 909 (Or. 1920)

Most recent

  1. Wilson v. Clark464 P.2d 683 (Or. 1970)
  2. Universal Electric Const. Co. of Alabama v. Robbins194 So. 194 (Ala. 1940)
  3. State ex rel. Southern Pacific Co. v. American Surety Co.44 P.2d 1079 (Or. 1935)
  4. State ex rel. Dixon v. Kuckenberg-Wittman Co.26 P.2d 568 (Or. 1933)
  5. Williamson v. Williams247 N.W. 704 (Mich. 1933)
  6. Royal Indemnity Co. v. Independence Indemnity Co.29 F.2d 43 (9th Cir. 1928)

Citing references are not a citator: they show that a later opinion cites this case, not whether it followed, distinguished, or overruled it. Check negative history before relying on this case.

Authorities cited 3

DepthCaseCited by
Multnomah Cnty. v. United States Fid. & Guar. Co., 170 P. 525 (Or. 1918) 22
Hogan v. Cushing, 5 N.W. 490 (Wis. 1880) 21
Chicago & Northeastern R.R. v. Sturgis, 7 N.W. 213 (Mich. 1880) 21

Keyboard shortcuts

/Focus the search box
j kNext / previous result
EnterOpen the selected result
xAdd / remove the selected result from the download list
n pNext / previous search term in a case
cCopy the citation of the current case
+ −Larger / smaller reading text
?Show this list