Bill Harbert Constr. v. Cortez Byrd, 169 F.3d 693 (11th Cir. 1999)
Download
Format
Include

Star paging (*137) is kept for pin cites.

Subsequent history: rev'd, Cortez Byrd Chips, Inc. v. Bill Harbert Constr. Co., 529 U.S. 193 (2000). (read from the later opinion; check before relying)

Court
Court of Appeals for the Eleventh Circuit · U.S. Courts of Appeals
Decided
March 9, 1999
Docket
No. 98-6404
Citations
169 F.3d 6931999 U.S. App. LEXIS 3638

Opinion

PUBLISH IN THE UNITED STATES COURT OF APPEALS FOR THE ELEVENTH CIRCUIT ________________________ FILED No. 98-6404 U.S. COURT OF APPEALS Non-Argument Calendar ELEVENTH CIRCUIT ________________________ 03/09/99 THOMAS K. KAHN D. C. Docket No. C V-98-G-117-S CLERK

BILL HARBERT CONSTRUCTION COMPANY, a division of Bill Harbert International, Inc., Plaintiff - Counter-Defendant, Appellee, versus

CORTEZ BYRD CHIPS, INC., Defendant - Counter-Claimant, Appellant.

________________________ Appeal from the United States District Court for the Northern District of Alabama _________________________ (March 9, 1999)

Before TJOFLAT and EDMONDSON, Circuit Judges, and RONEY, Senior Circuit Judge.

PER CURIAM:

This case arises out of a dispute over an arbitration award that was confirmed by the district

court for the Northern District of Alabama. The sole issue on appeal is whether venue was proper

in that court. We affirm.

Plaintiff, Bill Harbert Construction Company, entered into an agreement to build a wood chip

mill for defendant, Cortez Byrd Chips, Inc., in Brookhaven, Mississippi. The agreement provided for arbitration of “[a]ll claims or disputes between the contractor and the owner arising out of or

relating to the contract, or the breach thereof....” While the agreement expressly stated that

Mississippi law was applicable, it did not provide for jurisdiction in a particular court, nor did it

specify venue for confirmation or vacatur/modification of an award. It merely stated that “judgment

may be entered upon [the arbitration award] in accordance with applicable law in any court having

jurisdiction thereof.”

After a dispute arose between the two, Harbert Construction filed a demand for arbitration

with the Atlanta, Georgia office of the American Arbitration Association. An arbitration panel

conducted an arbitration proceeding in Birmingham, Alabama from Tuesday, November 18, 1997

through Friday, November 21, 1997. On December 20, 1997, the arbitrators rendered their award

in favor of Harbert Construction.

Byrd filed a complaint to vacate and/or modify the arbitration award in the United States

District Court for the Southern District of Mississippi on January 13, 1998. On January 20, 1998,

Harbert filed this action in the Northern District of Alabama to confirm the arbitration award on

January 20, 1998. Byrd filed an answer, counterclaim and motion to dismiss, transfer or stay this

action. The district court denied Byrd’s motion, holding that venue was properly in the Alabama

district court, and entered final judgment in favor of Harbert for the net sum of $274,256.90 plus

costs and interest.

On appeal, Byrd alleges the district court erred in denying his motion because according to

a recent Fifth Circuit decision, venue is permissive and is proper in the district court in Mississippi

because he filed his action there first. We review the venue question de novo.

2 The Federal Arbitration Act states that a motion to confirm an arbitration award1 or to vacate

an award2 “may” be made to the United States court in and for the district within which such award

was made. 9 U.S.C. §§ 9 , 10.

In determining the propriety of its venue, the district court relied on our decision in Naples

v. PrePakt Concrete Co., 490 F.2d 182,184 (5th Cir.), cert. denied, 419 U.S. 843 (1974). In Naples,

this Court held that the Act’s venue provision places venue exclusively within the district court in

and for the district within which the arbitration award was made. Byrd asks us to follow instead the

holding of a more recent Fifth Circuit decision, Sutter Corp. v. P&P Indus., Inc., 125 F.3d 914 (5th

Cir. 1997), in which that court held venue under §§ 9 and 10 to be permissive3. Although the Sutter

Corp. opinion indicated that Naples v. PrePakt Concrete Co. did not decide this issue, it appears to

us that it controls this panel’s decision:

[I]n view of § 9's command, and for reasons of judicial restraint and comity, the district judge [in Florida] should have declined to enjoin the confirmation proceedings in the Ohio district court [district within which the award was made]. See Naples, 490 F.2d at 184 .

1 If no court is specified in the arbitration agreement, an application for an order confirming the award “may be made to the United States court in and for the district within which such award was made.” 9 U.S.C. §9 . 2 Under certain circumstances, “the United States court in and for the district wherein the award was made may make an order vacating the award upon the application of any party to the arbitration...” 9 U.S.C.§ 10. 3 There is a significant split of authority in the U. S. Courts of appeal as to whether these venue provisions are permissive or mandatory. See, e.g., In re VMS Securities Litigation, 21 F.3d 139 (7th Cir. 1994) (§ 10 permissive); Sunshine Beauty Supplies, Inc. v. United States District Court for Central Dist. of Cal., 872 F.2d 310 (9th Cir. 1989) (§ 9 mandatory); Smiga v. Dean Witter Reynolds, Inc., 766 F.2d 698

(2d Cir. 1985) (§ 9 permissive), cert. denied, 475 U.S. 1067 (1986); Central Valley Typographical Union No. 46 v. McClatchy Newspapers, 762 F.2d 741 (9th Cir. 1985) (§ 10 mandatory); Island Creek Coal Sales Co. v. City of Gainesville, Florida, 729 F.2d 1046 (6th Cir. 1984) (§ 9 mandatory). The Supreme Court has never resolved this conflict.

3 We are bound to follow this Court’s prior precedent. Fifth Circuit decisions prior to October

1, 1981 are binding precedent on this Court, but not after that date1981. See Bonner v. City of

Prichard, 661 F.2d 1206,1209 (11th Cir. 1981). Accordingly, the district court’s decision is due to

be affirmed.

AFFIRMED.

4

How later courts describe this case

No later court has written an explanatory parenthetical about this case yet.

1999: 219992026peak 1999 · 2

Relies on it most ⓘ

  1. P&P Industries, Inc. v. Sutter Corporation179 F.3d 861 (10th Cir. 1999)
  2. Triad System Financial Corp. v. Stewart's Auto Supply, Inc.47 F. Supp. 2d 1332 (N.D. Ala. 1999)

Most recent

  1. P&P Industries, Inc. v. Sutter Corporation179 F.3d 861 (10th Cir. 1999)
  2. Triad System Financial Corp. v. Stewart's Auto Supply, Inc.47 F. Supp. 2d 1332 (N.D. Ala. 1999)

Citing references are not a citator: they show that a later opinion cites this case, not whether it followed, distinguished, or overruled it. Check negative history before relying on this case.

Authorities cited 8

DepthCaseCited by
City of Naples v. The Prepakt Concrete Co. & Am. Employers' Ins. Co., 490 F.2d 182 (5th Cir. 1974) 34
Bonner v. City of Prichard, 661 F.2d 1206 (11th Cir. 1981) 10,536
Cortez Byrd Chips, Inc. v. Bill Harbert Constr. Co., 529 U.S. 193 (2000) 178
Marcy Smiga v. Dean Witter Reynolds, Inc., 766 F.2d 698 (2d Cir. 1985) 117
Sutter Corp. v. P & P Indus., 125 F.3d 914 (5th Cir. 1997) 96
Island Creek Coal Sales Co. v. City of Gainesville, 729 F.2d 1046 (6th Cir. 1984) 54
Cent. Valley Typographical Union, No. 46 v. McClatchy Newspapers, 762 F.2d 741 (9th Cir. 1985) 42
In re Vms Sec. Litig.., 21 F.3d 139 (7th Cir. 1994) 26

Keyboard shortcuts

/Focus the search box
j kNext / previous result
EnterOpen the selected result
xAdd / remove the selected result from the download list
n pNext / previous search term in a case
cCopy the citation of the current case
+ −Larger / smaller reading text
?Show this list