TaiLexi AI U.S. Case Law

Hopkins v. Sanford

John W. Hopkins and William M. Ferry v. Samuel R. Sanford and Samuel B. Peck

Hopkins v. Sanford, 38 Mich. 611 (1878)
Download
Format
Include

Star paging (*137) is kept for pin cites.

Court
Michigan Supreme Court · State Highest Courts
Decided
April 9, 1878
Judges
Marston, Other
Citations
38 Mich. 6111878 Mich. LEXIS 132
Headnotes
Logging contract — Advances—Mutual obligation — Damages. A flrig of loggers contracted to provide four million feet of logs for sawing and had the option of furnishing logs to the amount of two millions more, the mill-owners to advance cash at the rate of $3 a thousand, as called for. Held that if the loggers called for advances beyond the proper amount for four million feet, they were also bound to furnish logs accordingly, and could not treat the extra advances as a loan. ■ Damages for breach of contract should be such as may fairly and reasonably be considered as arising from the breach itself, or to have been contemplated by . both parties when they made the contract as the probable result of the breach.
Summary
Error to Muskegon. Assumpsit on contract. Defendants bring error.

Syllabus and headnotes are prepared by the reporter or publisher, not the court, and are not part of the opinion.

Opinion of the Court — Marston

Text extracted by OCR from a scanned original; check the original for exact wording.

Marston, J.

The questions raised in this case depend upon the construction to be given the written contract in view of the advances made thereunder.

Under this contract Sanford & Peck were to procure from certain lands owned by them, during the winter and spring of 1870 and 1871 not less than four million, and from that up to six million of pine saw logs. Hopkins & Co. were to “advance in cash from time to time as called for, to the amount of three dollars per thousand feet, say twelve thousand dollars upon four million feet of logs, and relatively the same for a greater number of thousand feet.” Certain other advances were to be made but no question arises concerning them. The referee found “that during the time said logging job was going on, the defendants, Hopkins & Co., advanced money to the plaintiffs, to the amount of fifteen thousand dollars,” and also made the other advances according to the contract. The referee also-found as a conclusion of law, that under the circumstances Sanford & Peck were not bound to furnish over four million, and consequently were not liable in damages for a failure to deliver beyond that quantity.

In this view of the case we are of opinion the referee erred. It certainly was optional with Sanford & Peek in the first instance under them contract to put in any beyond the four million, but when from time to time they called for and received the advance of three dollars per thousand feet, they thereby obligated themselves to put in to the extent of such advances, — noi> exceeding the six million, — as under this clause of the *613 contract they could only call for an advance of three dollars upon each thousand feet put in by them. When they had received this advance upon four million feet, and afterwards called for and received three thousand dollars more, the only reasonable construction that could be placed thereon, under the contract, would be that they intended and thereby undertook to put in an additional million feet of logs. Under the contract they were entitled to this advance of fifteen thousand dollars, for the sole reason that they had or would put in, within the time fixed by the contract, five million feet, and they could not call for and receive this money under the contract, and then say that it was nothing but a loan. If they did not intend to bind themselves to put in over four million feet, they should have acted consistently with that intention, and not have called for advances which they were not entitled to, except upon the theory that they would put in to .exceed that quantity. The case of Davis v. Bush, 28 Mich., 432 , is decisive upon this question.

The judgment must therefore be reversed and a new trial ordered, but should we not direct attention to another question, it might be claimed that we approved of the measure of damages, adopted by the referee for non-delivery of the contract quantity of logs, viz.: f 1.50 per thousand feet, that being the profits on manufacturing under the contract. The rule laid down by the court of exchequer in Hadley v. Baxendale, 9 Exch., 341, has frequently been recognized and followed in this State. In cases of breach of contract the damages “should be such as may fairly and reasonably be considered either arising naturally, i. e. . according to the usual course of things, from such breach of contract itself, or, such as may reasonably be supposed to have been in the contemplation of both parties at the time they made the contract as the probable result of the breach of it.” Was it according to the usual course of things from the breach of the contract in this case, that the'mill *614 of Hopkins & Co. should lie idle? Or could they have obtained a sufficient supply of logs for that season, after the breach, from other sources, at the same or a less saw-bill? Or in case they could not, would such failure be a usual one, — something that might naturally and reasonably have been expected, — or was it owing to special and peculiar circumstances existing at that time? Or under the other theory, could the parties at the time the agreement was made, or at the time the advances over and above for the four million were made, reasonably be supposed to have contemplated the fact that the mill would have to lie idle, as the probable result of the failure to put in the five million feet or any part thereof ? As the case now stands under the finding of the referee, these questions may not be free from doubt, but as the showing upon a new trial may assume a somewhat different aspect, we express no opinion upon these questions.

The judgment must be reversed with costs and a new trial ordered.

The other Justices concurred.

How later courts describe this case

No later court has written an explanatory parenthetical about this case yet.

Cited by 10 cases

View all citing references →
1881–1882: 11893–1894: 11897–1898: 11915–1916: 31917–1918: 21967–1968: 11979–1980: 118812026peak 1915 · 3

Relies on it most ⓘ

  1. State Mutual Cyclone Insurance v. O & a Electric Cooperative161 N.W.2d 573 (Mich. 1968)
  2. Industrial Works v. Mitchell72 N.W. 25 (Mich. 1897)
  3. Frederick v. Hillebrand165 N.W. 810 (Mich. 1917)
  4. Atlas Concrete Pipe, Inc. v. Roger J. Au & Son, Inc.467 F. Supp. 830 (E.D. Mich. 1979)
  5. Farmers' Savings Bank v. Jameson175 Iowa 676 (1916) · Concurrence
  6. Wolf v. Megantz151 N.W. 622 (Mich. 1915)

Most recent

  1. Atlas Concrete Pipe, Inc. v. Roger J. Au & Son, Inc.467 F. Supp. 830 (E.D. Mich. 1979)
  2. State Mutual Cyclone Insurance v. O & a Electric Cooperative161 N.W.2d 573 (Mich. 1968)
  3. Lewistown Iron Works v. Vulcan Process Co.165 N.W. 1071 (Minn. 1918)
  4. Frederick v. Hillebrand165 N.W. 810 (Mich. 1917)
  5. Farmers' Savings Bank v. Jameson175 Iowa 676 (1916) · Concurrence
  6. Feldman v. Wear-U-Well Shoe Co.157 N.W. 395 (Mich. 1916)

Citing references are not a citator: they show that a later opinion cites this case, not whether it followed, distinguished, or overruled it. Check negative history before relying on this case.

Authorities cited 1

DepthCaseCited by
Davis v. Bush, 28 Mich. 432 (1874) 8

Keyboard shortcuts

/Focus the search box
j kNext / previous result
EnterOpen the selected result
xAdd / remove the selected result from the download list
n pNext / previous search term in a case
cCopy the citation of the current case
+ −Larger / smaller reading text
?Show this list