TaiLexi AI U.S. Case Law

Smith v. Ross

Matthew B. Smith v. Andrew Ross and Dewitt C. Spaulding

Smith v. Ross, 16 N.W. 258 (Mich. 1883)
Download
Format
Include

Star paging (*137) is kept for pin cites.

Court
Michigan Supreme Court · State Highest Courts
Decided
June 20, 1883
Judges
Campbell, Other
Citations
16 N.W. 25851 Mich. 1161883 Mich. LEXIS 533
Disposition
Keversed.
Headnotes
Gontraat — Oom/non counts — Averment of demand — Costs. Certain building contractors agreed that when they got the payment ore the contract they would pay a certain sum to a specified person on an order from the painter. Held that an action for this money could not be brought until after the order had been presented or some demand made; and that if the agreement implied an obligation on. defendants’ part to take active measures to collect the money, the' failure to do so must be averred. Costs of both courts were allowed on reversal where recovery was had on a declaration which made out no cause of action.
Summary
Error to the Superior Court of Detroit: (Chipman, J.). Assumpsit. Defendants bring error. Where time of payment is regulated by the occurrence of a certain event, recovery cannot be had without proof of its occurrence: Breaux v. Lauve 21 La. Ann. 179; Snell v. Cheney 88 Ill. 258 ; Wolf v. Ma/reh 54 Cal. 228 ; Dr alte v. Kill 58 la. 37 ; Wiggins v. Gill 59 Tenn. 140; Beleher v. Loveland 119 Mass. 539; Thompson v. Houston 31 Tex. 610. A promise to pay money, when the promisor recovers his demands of a third person, is absolute, though he has no such demands, or does not use reasonable diligence to collect them: White v. Snell 5 Pick. 425.

Syllabus and headnotes are prepared by the reporter or publisher, not the court, and are not part of the opinion.

Opinion of the Court — Campbell

Text extracted by OCR from a scanned original; check the original for exact wording.

CaMpbell, J.

In this case defendants became assignees of a contractor named Spier, who had a contract to build some houses for one Dinan. After taking the assignment, they made arrangements to complete the houses, and plaintiff desired to get a job of painting for $200. Thereupon one J. A. Degaw, to enable him to do so, undertook to become security, as the parties termed it. Degaw entered into a written contract with defendants on the 21st of November, 1881, which is the only contract in writing bearing on the Issue, and which is agreed to be the contract under which plaintiff sets up his rights. Plaintiff’s name does not appear in it, although he was the intended painter.

By this paper Degaw agreed to become security for the painting of the houses, and to pay any damages for any delay, — “ the same to be commenced to-day.” Defendants agreed, upon the completion of said work and acceptance by the architect, “ to pay to John A. Degaw the sum of two hundred dollars, when he presents order from painter, the money to be paid when A. Boss and Spaulding gets the last payment upon said contract.” The buildings were accepted by the architect in January, 1882, when, if the contract had been properly performed, the land-owner, Mr. Dinan, was bound to pay. Dinan, however, refused to pay, and on defendants’ suing him, tied up the case in chancery, and they did not get their pay till after this suit was commenced.

Neither Smith nor Degaw ever demanded jjayment before suit brought, and Smith never gave Degaw an order for payment.

Defendants asked the court to hold that no cause of action had been made out, which was refused. The court put the case to the jury that unless defendants used diligence to collect the debt from Dinan they were liable for principal and interest from such time as it might have been collected.

*118 This was an action on the common counts entirely. The-parties seem to make no question as to Smith being entitled to the money, and put the case on the other questions. And’ the defendants insist that inasmuch as the suit is for the price or value and there is no averment of negligence or failure on the part of defendants to do their duty, there is' no ground of recovery strictly at all, and none to recover interest or costs, the principal being now arranged.

We think the defense is correct. A suit on the terms of the contract only entitled the party to be paid when defendants were paid. If, as is probable, this implied an obligation to take active measures to collect the money, the failure to do so should have been specially averred as well as shown, and this was not done. We have not ourselves discovered evidence of any lack of diligence. And it is also plain under the contract that inasmuch as ■ they were to pay Degaw and not plaintiff, and then only on a written order, it is difficult to see how they could be held at fault, unless, by presentation of such order or other demand before suit, they were put under obligation to meet the claim.

As the record is presented to us the judgment should be' reversed with costs and a new trial granted. As no cause of action at all was made out under the declaration, the defendants should have prevailed below and should have-had costs there.

The other Justices concurred.

How later courts describe this case

No later court has written an explanatory parenthetical about this case yet.

1913: 11924: 11930: 119132026peak 1913 · 1

Relies on it most ⓘ

  1. Peaslee v. Gordon Falls Electric Co.135 P. 521 (Or. 1913)
  2. McIntosh v. Groomes198 N.W. 954 (Mich. 1924)
  3. Ballas v. Lake Weir Light & Water Co.130 So. 421 (Fla. 1930)

Most recent

  1. Ballas v. Lake Weir Light & Water Co.130 So. 421 (Fla. 1930)
  2. McIntosh v. Groomes198 N.W. 954 (Mich. 1924)
  3. Peaslee v. Gordon Falls Electric Co.135 P. 521 (Or. 1913)

Citing references are not a citator: they show that a later opinion cites this case, not whether it followed, distinguished, or overruled it. Check negative history before relying on this case.

Authorities cited 0

No citations to other opinions in this database were found.

Keyboard shortcuts

/Focus the search box
j kNext / previous result
EnterOpen the selected result
xAdd / remove the selected result from the download list
n pNext / previous search term in a case
cCopy the citation of the current case
+ −Larger / smaller reading text
?Show this list