People ex rel. Sauer v. Connell

PEOPLE, for use of SAUER v. CONNELL

People ex rel. Sauer v. Connell, 161 N.W. 844 (Mich. 1917)
Download
Format
Include

Star paging (*137) is kept for pin cites.

Court
Michigan Supreme Court · State Highest Courts
Decided
March 29, 1917
Docket
No. 108
Judges
Bird, Brooke, Kuhn, Moore, Ostrander, Person, Steere, Stone
Citations
161 N.W. 844195 Mich. 771917 Mich. LEXIS 655
Disposition
Affirmed.
Headnotes
1. Schools and School Districts — Public Works — Contracts— Subcontractors. Where plaintiffs agreed to and did manufacture the interior finish for a school house in conformity with the plans and specifications of the architects, they were subcontractors. 2. Same — Public Works — Bonds — Notice — Sufficiency — Statutes. In a suit upon a bond given by. a contractor to a school board for the protéction of subcontractors and laborers upon a school house under the provisions of section 2, Act No. 187, Pub. Acts 1905 (3 Comp. Laws 1915, § 14827), where plaintiffs, subcontractors,' notified the school board by letter that they had contracted to furnish certain material, part of which had been delivered, stating the amount due them, said notice was a -sufficient compliance with the act, in view of the fact that the contract had been so modified that payment could be made by the school board direct to the materialmen and laborers; ‘ and. it was unnecessary for plaintiffs to notify the board that they relied on the bond, or to notify the principal contractor that this notice had been given to the board, as required by the act, since these requirements were to enable the officials to withhold funds sufficient to pay the subcontractor and to give notice thereof to the contractor so that he would not attempt to overdraw his account.1
Summary
Error to Wayne; Davis, J., presiding. Assumpsit by Charles A. Sauer and Adam Sauer, copartners as C. A. Sauer & Company, in the name of the people of the State of Michigan, against Edward A. Connell, principal, and the Massachusetts Bonding & Insurance Company, surety, on a surety bond. Judgment for plaintiffs. Defendants bring error.

Syllabus and headnotes are prepared by the reporter or publisher, not the court, and are not part of the opinion.

Opinion of the Court — Bird

Text extracted by OCR from a scanned original; check the original for exact wording.

Bird, J.

Defendant Edward A. Connell entered into a contract with the board of education of the city of Detroit on the 6th day of November, 1911, to construct a school building to be known as the “Caroline Cross-man School,” for the consideration of $77,281. The building was to be erected in accordance with the plans and specifications drawn by Malcomson & Higginbotham, architects. At the time the contract was executed, the board demanded and received from Connell a bond in compliance with Act No. 187, Pub. Acts 1905 (3 Comp. Laws 1915, § 14827). The bond was in the penal sum of $77,281, with defendant Massachusetts Bonding & Insurance Company as surety. After this contract had been executed, and on the 24th day of January, 1912, defendant Connell entered into a contract with plaintiffs to furnish certain interior finish, which Connell was obliged to furnish under his contract, for the consideration of $4,958. Connell proceeded with the work until November 14, 1912, when the contract was modified by consent of all parties, including the surety, so that payment could be made by the board of education direct to the materialmen and laborers. At the date of modification, Connell was indebted to the plaintiffs in the sum of $1,000, and Connell had received on his contract $31,-585.28. After the modification, the board paid out directly to materialmen and laborers $47,429.43. A settlement of the original contract took place between the board and Connell on January 22, 1914, and it *79 was found that the board had paid out $847.71 in excess of the contract price. Later and in the year 1915, Connell was allowed a bill for extras of $4,-633.74. After deducting the previous overpayment and certain other amounts on account of unfinished work, he was paid the sum of $3,043.53. The $1,000 which was owing to plaintiffs prior to the modification of the contract being still unpaid, this suit was brought to recover the amount together with the interest thereon. The defendants offered no testimony, but requested a directed verdict. This request was denied, and a verdict was directed in accordance with plaintiffs,’ demand. Defendant surety company alone has appealed. Its counsel argue two questions:

(1) That the trial court was right in holding that plaintiffs were subcontractors.

(2) That the trial court was in error in holding that any recovery could be had because plaintiffs neglected to give the notice required by section 2 of said act.

- 1. The rule which appears to have been laid down by this court to determine in any given case whether one is a subcontractor or-a materialman is as, follows:

"Has he. agreed that the original contract shall be the standard by which the performance of his contract shall be judged?” People v. Campfield, 150 Mich. 675 ( 114 N. W. 659 ).

The entire agreement between plaintiffs and Connell does not appear in the record, due probably to the fact that Chas. A. Sauer died a few days before the trial; but we think a fair inference may be drawn from the testimony that plaintiffs agreed to and did manufacture the interior finish in conformity with the plans and specifications of the architects. We therefore conclude that the trial court was right in holding that the plaintiffs were “subcontractors.”

2. Counsel’s second and principal contention is that *80 no recovery can be had against the defendant surety company because section 2 of Act No. 187, Pub. Acts 1905 (3 Comp. Laws 1915, § 14828), was not complied with in giving the notice therein required. The material portion of the section provides that:

“In the case of a subcontractor, he shall give notice in writing before payment is made for the work or materials furnished by him, to the said board of officers or agents, that he is a subcontractor for the doing of some part of such work which he shall specify in his notice and that he relies upon the security of the bond by this act required to be given by the principal contractor, and that in the case of the giving of such notice to the said board of officers or agents said subcontractor shall also notify the - principal contractor that he has. done so, and whenever this shall have been done, the said subcontractor shall be entitled, subject to the rights of the persons with whom he has contracted for labor and materials, to the benefit of the security given by the principal contractor.”

The essentials of this section are:

(а) That the subcontractor shall give notice to the officials, that he has entered into a contract with the principal contractor to do some part of the work.

(б) That he shall give such notice in writing before the principal contractor shall be paid for the work and materials so furnished by him.

(c) That he relies upon the security of the bond.

(d) That he shall notify the principal contractor that he has given this notice to the officials.

It is conceded that no formal notice embracing these essentials was given by the plaintiffs, but it is claimed that a letter written by them to the board of education in October, 1912, just prior to the modification of the contract, was a substantial compliance with this section. The letter follows:

“We beg to advise you that on January 25th, 12, we entered into a contract with Mr. ■ E. A. Connell, contractor for the Crossman School Bldg., to furnish material as enumerated on the enclosed copy of our *81 contract. We have made delivery of upwards of $2,-000.00 of this material upon which we have received $1,000.00, leaving a balance of $1,000.00 due. We also have all material manufactured ready for shipment awaiting instructions. In the event that the contract for balance of work on this building is taken out of Mr. Connell’s control we would appreciate it very much to have you advise us. Thanking you for your consideration, we are, * *

We think the notice contained in this letter was a full compliance with essential “a” and a reasonable compliance with essential “6.” When the letter was written, less than half of the contract price had been paid to the contractor, and the major part of the interior finish had not yet been delivered to the contractor in Detroit. The letter does not, however, satisfy the essentials “c” and “cl.” So far as the reasons are apparent for inserting these requirements, they were to enable the officials to withhold funds sufficient to pay the subcontractor and to give notice thereof to the contractor so that he would not attempt to overdraw his account which should accrue from time to time upon estimates. If this be the proper view, we can see no reason for complying with essentials “c” and “d,” because the board had taken into .its own hands the whole matter of making disbursements to materialmen, laborers, and subcontractors.

Having in mind the very liberal construction which this court has given the statute (People v. Traves, 188 Mich. 415 [ 154 N. W. 120 ]), we are constrained to hold that this letter is a substantial compliance with section 2. The case of People v. Finn, 162 Mich. 481 ( 127 N. W. 704 ), is urged upon our attention as being opposed to this view; but we think the cases are distinguishable. In the Finn Case no notice at all was served. ■ In this case a somewhat belated notice was served; but defendant surety company has not made *82 it appear that it has been injured thereby, consequently it has no ground for complaint. People v. Bowen, 187 Mich. 257 ( 158 N. W. 672 ); People v. Traves, 188 Mich. 345 ( 154 N. W. 130 ).

The judgment of the trial court will be affirmed.

Kuhn, C. J., and Stone, Ostrander, Moore, Steere, and Brooke, JJ., concurred. Person, J., did not sit.

How later courts describe this case

No later court has written an explanatory parenthetical about this case yet.

1918: 11921: 11929: 11930: 11942: 11943: 11975: 219182026peak 1975 · 2

Relies on it most ⓘ

  1. Hub Electric Co. v. Aetna Casualty & Surety Co.400 F. Supp. 77 (E.D. Mich. 1975)
  2. Charles W. Anderson Co. v. Argonaut Insurance233 N.W.2d 691 (Mich. Ct. App. 1975)
  3. F. J. Lewis Mfg. Co v. Snyder37 F.2d 299 (6th Cir. 1930)
  4. Christman v. Southern Surety Co.43 F.2d 452 (W.D. Mich. 1929)
  5. Holt & Bugbee Co. v. City of Melrose41 N.E.2d 562 (Mass. 1942)
  6. Sandusky Grain Co. v. Borden's Condensed Milk Co.183 N.W. 218 (Mich. 1921)

Most recent

  1. Hub Electric Co. v. Aetna Casualty & Surety Co.400 F. Supp. 77 (E.D. Mich. 1975)
  2. Charles W. Anderson Co. v. Argonaut Insurance233 N.W.2d 691 (Mich. Ct. App. 1975)
  3. People ex rel. Wheeling Corrugating Co. v. W. L. Thon Co.11 N.W.2d 886 (Mich. 1943)
  4. Holt & Bugbee Co. v. City of Melrose41 N.E.2d 562 (Mass. 1942)
  5. F. J. Lewis Mfg. Co v. Snyder37 F.2d 299 (6th Cir. 1930)
  6. Christman v. Southern Surety Co.43 F.2d 452 (W.D. Mich. 1929)

Citing references are not a citator: they show that a later opinion cites this case, not whether it followed, distinguished, or overruled it. Check negative history before relying on this case.

Authorities cited 5

DepthCaseCited by
People ex rel. Buhl Sons Co. v. Finn, 127 N.W. 704 (Mich. 1910) 10
People ex rel. Davis v. Campfield, 114 N.W. 659 (Mich. 1908) 9
People ex rel. T. B. Townsend Brick & Contracting Co. v. Bowen, 187 Mich. 257 (1915) 15
People ex rel. H. Houghton & Sons v. Traves, 188 Mich. 345 (1915) 15
People ex rel. N.J. Terra Cotta Co. v. Traves, 188 Mich. 415 (1915) 10

Keyboard shortcuts

/Focus the search box
j kNext / previous result
EnterOpen the selected result
xAdd / remove the selected result from the download list
n pNext / previous search term in a case
cCopy the citation of the current case
+ −Larger / smaller reading text
?Show this list