BERGLUND & PETERSON v. LEON ABRAM AND OTHERS. EARL WRIGHT

Berglund & Peterson v. Abram, 182 N.W. 624 (Minn. 1921)
Download
Format
Include

Star paging (*137) is kept for pin cites.

Court
Supreme Court of Minnesota · State Highest Courts
Decided
April 15, 1921
Docket
No. 22,118
Judges
Tayror
Citations
182 N.W. 624148 Minn. 4121921 Minn. LEXIS 549
Disposition
Affirmed.
Headnotes
Mechanic’s lien — owner must consent to improvements. 1. Improvements cannot be charged as a lien against land, unless made with the consent of the owner. Failure of owner to disclaim responsibility. 2. But the legislature may provide that an owner, who fails to disclaim responsibility for improvements made with his knowledge, shall be deemed to have authorized them. Part-owner’s interest liable to whole cost of improvements. 3. The interest of a part-owner may be subjected to a lien for the entire cost of improvements made at his instance or with his consent. Statute — disclaimer of responsibility. 4. The statute provides, in effect, that all persons, except encumbrancers, having an interest in land, shall be deemed to have authorized improvements made thereon with their knowledge, “insofar as to subject their interests to liens therefor,’-’ unless they shall disclaim responsibility for such improvements in the prescribed manner. Liberal construction of mechanic’s lieu statute. 5. The purpose of the statute is to protect laborers and materialmen, and it should be liberally construed to accomplish that purpose. Lien founded on owner’s statutory duty. 6. The lien is founded on the duty which, under the statute, the owner owes to laborers and materialmen. Part-owner’s liability when he fails to disclaim responsibility. 7. Where only one of several part-owners knows that an improvement is being made and he fails to disclaim responsibility therefor, his interest in the land may be charged with a lien for the entire improvement.
Summary
Action in the district court for St. Louis county to recover $5,639.09 and enforce a mechanic’s lien for the same. The case was tried before Cant, ■ J., who made findings and as conclusions of law ordered judgment in favor of plaintiffs and certain defendants that the total judgment constitute a lien upon the undivided interest of Earl Wright in the premises and that interest be sold to satisfy the judgment. The motion of Earl Wright for amended findings and conclusions of law was denied. From an order denying his motion for a new trial, Earl Wright appealed.

Syllabus and headnotes are prepared by the reporter or publisher, not the court, and are not part of the opinion.

Opinion of the Court — Tayror

Text extracted by OCR from a scanned original; check the original for exact wording.

Tayror, C.

This action was brought to enforce mechanics’ liens against a certain lot in the city of Duluth. The owners of the lot are Sarah A. Wright, Jessie Wright James, Earl Wright and Fred B. Wright. Sarah A. Wright owns an undivided one-third of the lot and each of the others an undivided two-ninths thereof. In 1909 the four joint owners executed a ground lease of the lot to Leon Abram for a term of nearly 100 years and sold him the building thereon. In 1917, Abram made extensive improvements in the building, and the liens in question were filed for work performed and material furnished in making these improvements. Before the trial, Abram had been adjudged a bankrupt, and his ground lease had been canceled and annulled. The trial court found and determined the respective amounts due the several lien claimants, and further found that defendant Earl Wright had actual knowledge of the making of the improvements and neither gave nor posted any notice that they were not made at his instance, and further found that the other fee owners had no knowledge of the making of the improvements. As conclusions of law the court held that the several lien claimants were entitled to liens on the interest of defendant Earl Wright in the property for the full amount of their respective claims, but were not entitled to liens on the interest of any of the other fee owners. Defendant Earl Wright made a motion for a new trial and appeals from the order denying it. He will be designated as defendant hereinafter.

Defendant’s counsel state in their brief: “The court below charged *414 Earl Wright’s two-ninths interest with the entire nine-ninths of this lien¡ Appellant Earl Wright concedes that his interest is subject to a two-ninths part of this lien, but denies that it is subject to the other seven-ninths. This is the question which is raised, in the last analysis, by all the assignments of error. Hence we will not deal with the assignments of error separately but will discuss this one issue.”

They contend that, if the entire cost of the improvement is enforced against defendant’s undivided two-ninths interest in the property, it will result in taking his property without due process of law, and present a forceful argument in support of their contention.

The statute provides: “When improvements are made by one person on the land of another, all persons interested therein otherwise than as bona fide prior encumbrancers or lienors shall be deemed to have authorized such improvements, insofar as to subject their interests to liens therefor. But any person who has not authorized the same may protect his interest from such liens by serving upon the persons doing work or otherwise contributing to such improvements, within five days after knowledge thereof, written notice that the' improvement is not being made at his instance or by posting like notice, and keeping the same posted, in a conspicuous place on the premises.” 6. S. 1913, § 7024.

It is well settled that improvements made by one person on the land of another cannot be charged as a lien against the land, unless the improvements were made at the instance or with the consent of the landowner. Laird v. Moonan, 32 Minn. 358 , 20 N. W. 354 ; Meyer v. Berlandi, 39 Minn. 438 , 40 N. W. 513 ; Bardwell v. Mann, 46 Minn. 285 , 48 N. W. 1120 ; Wheaton v. Berg, 50 Minn. 525 , 52 N. W. 926 . But it is also well settled that the legislature may provide by statute that improvements made with the knowledge of the landowner shall be deemed to have been made at his instance, unless he disclaims responsibility therefor in the manner and within the time prescribed by the statute. Martin Lumber Co. v. Howard, 49 Minn. 404 , 52 N. W. 34 ; Wheaton v. Berg, 50 Minn. 525 , 52 N. W. 926 ; Congdon v. Cook, 55 Minn. 1 , 56 N. W. 253 ; Northwestern L. & W. Co. v. Parker, 125 Minn. 107 , 145 N. W. 964 .

Defendant knew the improvements in question were being made and did not give or post the notice provided for by the statute. He concedes *415 that under these circumstances the statute creates a lien against his undivided two-ninths interest in the property, but contends that the statute cannot create a lien against this interest for the entire co.st of the improvements, but only for the two-ninths part thereof which inured to this interest. In support of this contention he argues that liens for improvements made without express authority of the landowner can only be sustained on the theory that the improvements become a part of, and are beneficial to, the land; that the lien in question does not rest on any affirmative act of his, but wholly on the presumption of consent created by the statute; that the legislature cannot create a presumption that the improvements were made with his consent, unless the facts on which the presumption is founded furnish a rational basis for inferring such consent, and that the fact that he knew of the making of the improvements, without disclaiming responsibility therefor, furnishes no rational basis for inferring that he consented that the seven-ninths part of the improvements which inured to the other part-owners of the property should be charged against his two-ninths interest therein. He states frankly that he has been unable to find any case in which the question which he raises has been decided or discussed. Plaintiff cites many- cases, of which Ness v. Wood, 42 Minn. 427, 44 N. W. 313 ; Ness v. Davidson, 49 Minn. 469 , 52 N. W. 46 ; Mellor v. Valentine, 3 Colo. 260 ; Roxbury P. & D. Co. v. Nute, 233 Mass. 112 , 123 N. E. 391 , 4 A. L. R. 680, are examples, in which the interest of one part-owner has been subjected to a lien for the entire cost of improvements made to the common property, but defendant answers that in all these cases the consent of the part-owner was either expressly given or could he implied from the facts proven without the aid of any statutory presumption, and that the question which he raises was not involved or considered in any of them.

While we have read defendant’s able and ingenious argument with much interest, we are unable to accept all his premises or to concur in his conclusion. The statute provides that, where improvements are made by one person on the land of another, all persons having an interest in the land, otherwise than as encumbrancers or lienors, "shall be deemed to have authorized such improvements insofar as to subject their interests to liens therefor,” unless they give or post notice, within five days after *416 knowledge thereof, that the improvements are not being made at their instance.

The purpose of the statute is to protect laborers and materialmen bj giving them a lien on the property for the value of the work and material they contribute toward its improvement. To remove grounds for controversy and to make the protection intended more certain and effective, the statute imposes on every person, having an interest in the property and who knows that improvements are being made thereon which he has not authorized, the duty to warn the laborers and material-men concerned that' the improvements are not being made at his instance, and provides that if he fails to give such warning he “shall be deemed to have authorized such improvements” to the extent of subjecting his interest to a lien therefor.

That the legislature may impose such a duty on the owners of the property-for the protection of those who furnish labor or material for its improvement, and may make the failure of an owner to give or post the prescribed notice equivalent to an express acknowledgment that the improvement is being made at his instance, is no longer an open question. Wheaton v. Berg, 50 Minn. 525 , 52 N. W. 926 ; Congdon v. Cook, 55 Minn. 1 , 56 N. W. 253 ; Minneapolis Plumbing Co. v. Arcade Inv. Co. 124 Minn. 317 , 145 N. W. 37 ; Martin Lumber Co. v. Howard, 49 Minn. 404 , 52 N. W. 34 ; McCausland v. West Duluth Land Co. 51 Minn. 246 , 53 N. W. 464 ; Sandberg v. Palm, 53 Minn. 252 , 54 N. W. 1109 ; Fuquay v. Stickney, 41 Cal. 583 ; 18 R. C. L. 907, and cases there cited. And as the statute is remedial, it is to be liberally construed to accomplish the purpose for which it was enacted. Krengel v. Haslam, 118 Minn. 506 , 137 N. W. 11 ; Lindquist v. Young, 119 Minn. 219 , 138 N. W. 28 ; Atlas Lumber Co. v. Dupuis, 125 Minn. 45 , 145 N. W. 620 ; Johnson v. Starrett, 127 Minn. 138 , 149 N. W. 6 ; Lamoreaux v. Andersch, 128 Minn. 261 , 150 N. W. 908 .

As already stated, it is well settled that, where a part-owner contracts for or authorizes the making of an improvement on the common property, his interest therein may be subjected to a lien for the entire cost thereof, and defendant concedes that such is the law. Defendant, having had knowledge of the improvements in question and having failed to disclaim responsibility therefor, must be deemed to have authorized them *417 insofar as to subject Ms interest to a lien therefor. To authorize them means something more than merely giving permission to make them. It means an affirmative grant of the right to make them. Wallinder v. Weiss, 119 Minn. 412 , 138 N. W. 417 . By virtue of the statute, defendant stands in the same position as if he had expressly authorized the improvements in controversy. TMs brings him within the rule which subjects the interest of a part-owner to a lien for the cost of improvements made to the common' property at his instance. The lien in question finds its support in the duty which, under the statute, defendant owed to the laborers and materialmen. Having failed to perform that duty, his interest in the property could be lawfully charged with a lien for the amounts due these laborers and materialmen.

Order affirmed.

How later courts describe this case

Explanatory parentheticals written by citing courts — 1 in all; the most informative distinct ones are shown.

Cited by 14 cases

View all citing references →
1923: 21926: 11941: 11942: 21944: 11947: 11960: 11968: 21977: 11985: 11995: 119232026peak 1923 · 2

Relies on it most ⓘ

  1. Master Asphalt Co. v. Voss Construction Co.535 N.W.2d 349 (Minn. 1995)
  2. Barry v. Barry26 N.W.2d 1 (Neb. 1947)
  3. Anderson v. Harrison160 N.W.2d 560 (Minn. 1968)
  4. Korsunsky Krank Erickson Architects, Inc. v. Walsh370 N.W.2d 29 (Minn. 1985)
  5. Nasseff v. Schoenecker253 N.W.2d 374 (Minn. 1977)
  6. Rochester's Suburban Lumber Company v. Slocumb163 N.W.2d 303 (Minn. 1968)

Most recent

  1. Master Asphalt Co. v. Voss Construction Co.535 N.W.2d 349 (Minn. 1995)
  2. Korsunsky Krank Erickson Architects, Inc. v. Walsh370 N.W.2d 29 (Minn. 1985)
  3. Nasseff v. Schoenecker253 N.W.2d 374 (Minn. 1977)
  4. Rochester's Suburban Lumber Company v. Slocumb163 N.W.2d 303 (Minn. 1968)
  5. Anderson v. Harrison160 N.W.2d 560 (Minn. 1968)
  6. Bond Electric Co. v. Mill City Plastics, Inc.102 N.W.2d 281 (Minn. 1960)

Citing references are not a citator: they show that a later opinion cites this case, not whether it followed, distinguished, or overruled it. Check negative history before relying on this case.

Authorities cited 21

DepthCaseCited by
Wheaton v. Berg, 52 N.W. 926 (Minn. 1892) 14
Congdon v. Cook, 56 N.W. 253 (Minn. 1893) 7
John Martin Lumber Co. v. Howard, 52 N.W. 34 (Minn. 1892) 4
Meyer v. Berlandi, 1 L.R.A. 777 (Minn. 1888) 64
Lamoreaux v. Andersch, 150 N.W. 908 (Minn. 1915) 41
Laird v. Moonan, 20 N.W. 354 (Minn. 1884) 36
Northwestern Lumber & Wrecking Co. v. Parker, 145 N.W. 964 (Minn. 1914) 33
Johnson v. Starrett, 149 N.W. 6 (Minn. 1914) 31
Ness v. Davidson, 52 N.W. 46 (Minn. 1892) 13
Lindquist v. Young, 138 N.W. 28 (Minn. 1912) 13
Bardwell v. Mann, 48 N.W. 1120 (Minn. 1891) 12
Sandberg v. Palm, 54 N.W. 1109 (Minn. 1893) 12
Ness v. Wood, 44 N.W. 313 (Minn. 1890) 11
Atlas Lumber Co. v. Dupuis, 145 N.W. 620 (Minn. 1914) 11
Wallinder v. Weiss, 138 N.W. 417 (Minn. 1912) 8
McCausland v. West Duluth Land Co., 53 N.W. 464 (Minn. 1892) 7
Minneapolis Plumbing Co. v. Arcade Inv. Co., 145 N.W. 37 (Minn. 1914) 5
Krengel v. Haslam, 137 N.W. 11 (Minn. 1912) 4
Roxbury Painting & Decorating Co. v. Nute, 233 Mass. 112 (1919) 16
Fuquay v. Stickney, 41 Cal. 583 (1871) 7
Mellor v. Valentine, 3 Colo. 260 (1877) 3

Keyboard shortcuts

/Focus the search box
j kNext / previous result
EnterOpen the selected result
xAdd / remove the selected result from the download list
n pNext / previous search term in a case
cCopy the citation of the current case
+ −Larger / smaller reading text
?Show this list