Summary
From the chancery court of Oktibbeha county.
Hon. T. B. Graham, Chancellor.
The appellees, B. M. & J. M. Brooks, citizens of the state of Georgia, contracted on June 9, 1888, with the appellant company to build and construct for it eleven miles of railroad in this state. The contract, which is mainly set out in a printed form, contained an extended and minute specification of the terms upon which the work was to be performed, and the conditions upon which the price was to be paid.
Before executing the contract, the said appellees signed and delivered to the appellant a written proposal or offer to do the work upon the conditions and according to the specifications of the above mentioned contract and at certain stated prices.
In this proposal the said appellees, among other things, certified that they had personally and carefully examined that portion of the line or division of the projected railroad on which the said work was to be let, and having made such examination they proposed to perform the work on the terms and conditions and according to the specifications set out in the contract, and at prices therein stated.
On the same day the contract was signed on the part of the company and the said appellees. The provisions of the contract which mre material to be referred to here are as follows:
1. The said contractors were to begin work within fifteen days from the date of the contract, June 9, 1888, and to complete the •entire eleven miles by November 15, following. No charge should be made by the contractor for any hindrance or delay from any -cause in the progress of the work or any portion of it, but it might entitle them to an extension of the time fixed for the completion ■of the work sufficient in the judgment of the engineer to compensate for the detention. It was further agreed that no claim for ■damages, arising from delay that might occur in obtaining title to right of way should be made by the contractors; but if title was not obtained in three months from the date of the contract, then the contractors might' abandon the work upon the portion the title to which could not be acquired.
2. The company reserved the right to make changes in the grades, curves, embankments, etc., as the engineer should deem necessary and proper, subject to an allowance or deduction from the price as the work was increased or diminished thereby.
3. The contractors were prohibited from letting or transferring .their contracts or any part of it (except for delivery of work or material), or withdrawing their constant personal attention from the-work, without the written consent of the chief engineer indorsed on the contract.
4. No claim should be made for extra work unless the same should have been done in pursuance of a written order from the-engineer in charge, and the claim be made at the time of the first monthly payment after the work was executed, unless the engineer-at his discretion should direct the claim to be allowed.
5. The contractors should remove and rebuild without charge' any work which the engineer might consider defectively executed..
6. The measurement of quantities should be made in excavation before their removal, except that borrowed material, at the discretion of the engineer, might be measured in the bank. The excavation was divided into three kinds, viz.: earth, rotten limestone- and solid rock, and the prices per cubic yard graded accordingly.
7. The company should reserve ten per cent, of the amount due upon each estimate, and in the event the work was not finished in accordance with the specifications, and agreeably to the directions-of the engineer under the contract, on or before November 15,. 1888, the said reserved percentage should be forever forfeited by the contractors. The company also reserved the right to employ a sufficient force and complete the work, if it became apparent that the work would not be completed by the time agreed upon, the expenses thus incurred to be charged to the contractors.
8. Upon the completion of the work a final estimate by the-engineer should be made of the quality, character, and value of the work under the contract, and at every stage of the work it should be subject to the direction, inspection and acceptance of the engineer, who should determine, without appeal, what in any case a fair construction of the contract required to be done ' by either party and his measurements, classification and estimates, monthly or final, should be absolutely conclusive upon both parties.
The bill in this cause was exhibited against the appellant by the said contractors, R. M. & J. M. Brooks, certain of their creditors as hereinafter set out, and others who were sub-contractors under them in the building of the said sections of railroad. After setting out the terms of the aforesaid written contract, the bill alleges that the contract as originally drawn in duplicate provided for the building of only ten miles of said road, but the company added another mile to the work to be done, and inserted it in the contract-against the protest of said E. M.' & J. M. Brooks, who, as they allege, had never examined the work along said- mile, and knew nothing of its character ; that they were induced to permit the insertion of that mile into the contract on the false and fraudulent-representation that the’work upon it was easy, and of the same kind as that upon the other ten miles, and that the company would endeavor to find another contractor to take the one mile and release-them, and, failing in this, the company would pay for the work thereon such a fair compensation as it could afford to pay under-all the circumstances; that the said contractors had nothing to-guide them in reference to the character of the work on said mile,, except the profiles shown to them by the company at the time, and its statements in reference thereto, all indicating that the work was-very desirable ; that upon these assurances the contract- was signed by them ; that it was understood that the contract was not to be-effectual until it was also signed ' by said company, but the company has never signed the contract at all.
The bill further alleges that, contrary to the said profiles and. representations, the one mile was in a dense, heavily timbered swamp, through which the road could only be built at an enormous cost. Complainants also allege a similar misrepresentation and fraud on the p'art of the company in reference to another mile of' the work, which they claim they were induced to contract for by the false representations of the company’s engineers, and which, because of the wet character of the soil, was very difficult and expensive to construct; that the extra cost and outlay incurred by them in endeavoring to do the work on said two miles was very great, and they are justly entitled to additional compensation therefor.
Several sub-contractors under E. M. & J. M. Brooks have-joined in the bill as complainants. The bill sets out the several contracts made with them, -the sections of the work undertaken by each, and the work done by them. It is alleged that the sub-contractors agreed to fulfill the requirement of the contract as made by the company with E. M. & J. M. Brooks, and the latter agreed to pay each sub-contractor the money collected on his work from the company under the estimates of the engineers, and that each .sub-contractor thereby became the equitable assignee of the claim for his own work against the company to the amount agreed to be paid him ; that these sub-contractors have no claims against the ■contractors, except so far as their claims cañ be enforced against the company through the contractors, and to do this is the primary ■object of this suit.
It is also alleged that after said contractors went on the work ■and had sublet the contract as to some of the sections, the railroad •company made alterations in the grade of the road in certain places, which caused additional expense and loss to the sub-contractors as well as the contractors; that the company also failed to procure right of way to a certain part of the line, and this necessitated a suspension of work, and removal by one of the sub-contractors at a great loss and expense to another place.
The amounts claimed by the several sub-contractors are set out in the bill, aud a lien upon the debt due by the defendant to E. M. & J. M. Brooks is sought to be established.
The bill further alleges that before entering into the said contract the said E. M. & J. M. Brooks were required by the company to make a deposit of two thousand dollars as a guaranty that they would fulfill the contract on their part; that this deposit was not required by the written contract, and besides this the company reserved ten per cent, of the amount due upon each estimate, which by the terms of the contract was not to be paid until a final ■settlement, and was to be an indemnity to the company for any loss which might be sustained by the refusal or failure of the contractors to finish the work.
It is alleged that the work was delayed because of the wrongful acts and negligence of the engineer of the company in preparing the section for the contractors and staking it off; that various monthly settlements were made, based on the estimates of the said engineers, but that the engineers were acting solely in the interest of the company, and made false and fraudulent estimates, intending to-cheat and defraud the contractors and sub-contractors, and thus’ forced them to settle upon false under-estimates; that because of the losses and reverses due to the willful wrongs and frauds of the-company’s engineers, the said contractors were forced to abandon the work before its completion, the company refusing to give them any extension of time.
Several general creditors of R. M. & J. M. Brooks, who had sued out attachments and had writs of garnishment served on the-defendant, have joined as complainants in the bill.
The prayer of the bill is that the work done be remeasured and re-estimated, and full and proper amounts be allowed therefor;; that the contractors be released from further obligation and work under the contract; that extra pay be allowed for all raised grades;: that the liens by garnishment be enforced, and that the rights and claims of the complainants be fully adjusted between them; that full discovery be made by the defendant of all profiles and estimates necessary to a proper computation of the amount due; that liens be fixed upon the amount due R. M. & J. M. Brooks by the-company, in favor of each sub-contractor, and in favor of said R. M. & J. M. Brooks upon the said railway, and that the sub-contractors be subrogated to said lien as provided by the statute in reference to the liens of mechanics and contractors.
The defendant demurred to the bill, alleging among other causes:
1. That there was no equity in the bill.
2. That the bill shows that the complainants’ remedy at law is complete.
3. The improper joinder of the sub-contractors and creditors of R. M. & J. M. Brooks.
4. That the bill is’ multifarious in that it seeks relief based on both a repudiation and an acceptance of the written contract, and because it unites distinct and unconnected matters between different parties.
5. The complainants do not offer to do equity.
6. The bill shows an abandonment of the contract by the-contractors and yet claims the value of their services.
7. The various claims and demands of the complainants are repugnant to the written contract, and the bill itself shows that under the contract and the alleged facts they have no right to relief.
The demurrer was overruled, and the defendant appealed.
1. The written contract must govern. It cannot be rejected in part and accepted in part. 2 Pom. Eq., § 916, note 4, and § 897, note 1; 64 Miss. 258.
The bill is multifarious. It should not claim for work done at •contract prices, and also extra compensation not provided in the contract. Ranger v. Gh'eat Western Ry. Co., 5 H. L. Cas. 72, s. c. 27 Eng. L. & E. Rep., §§ 35, 38, 53, 54, 56, 58, 66, and 67 ; 2 Pom. Eq., §§ 915, 916. Complainants, however, ask for a quantum meruit when that suits them best, and the contract price when that .suits them best, and offer to restore nothing.
This is inadmissible. Could v. Cayuga Co. Ranh, 99 N. Y. ■333; 3 Am. & Eng. Encycl. of Law, 932, note 2.
2. Having voluntarily abandoned the work without notice to quit by the defendant, they cannot disavow the obligation of the contract and yet recover the reserved percentage. After discovering the fraud, they still acted on the contract as subsisting and binding and thus waived all right to relief for the fraud. Herrioh y. R. R. Co., 27 Vt. 673 ; 2 Pom. Eq., § 897 ; Hanson v. Field, 41 Miss. 715; Edwards v. Roberts, 7 S. & M. 544. The bill cannot be maintained as a bill to cancel the contract for fraud, and for damages. 2 Pom. Eq., § 897, note 1.
3. Nor can the bill be sustained as a bill to recover the value of work upon a quantum meruit, and for an accounting. 29 N. J. Eq. 175 ; 44 Miss. 717 ; 1 Pom. Eq., § 178; Herrioh v. R. R. Co., ■supra; nor as a bill for discovery. 48 Miss. 343; 58 lb. 643.
4. The remedy at law is adequate. Strong v. Krebs, 63 Miss. •338; Lea,rned y. Holmes, 49 1b. 290; 2 Pom. Eq., §§ 911,914. The accounting is not necessary nor is it properly asked for. If there are any data not accessible to complainants, discovery can be had at law as well as in equity.
5. Misjoinder of parties. The sub-contractors and general ■creditors of the contractors are improperly joined as complainants. The court cannot at the same time adjudicate the claim of the contractors with the company and the claim of their creditors against them. If they were judgment creditors the case might be •different.
6. The bill cannot be sustained on the theory of preventing a multiplicity of suits. To sustain such a theory the complainants, Brooks, would have to be threatened with many suits by their •creditors and sub-contractors, and then might enjoin them and perhaps join this appellant as a defendant. 1 Pom. Eq., § 243 ■et seq.
7. The bill shows that the contractors proceeded to perform the work without objection because of the alleged fraud or the extra •expense. The circumstances 'are not sufficient to raise a presumption of an implied contract to pay extra. 75 111. 496 ; 52 Pa. St. 214; Barker v. R. JR. Co., supra; 28 Conn. 491. There should have been, a prompt disaffirmance. 2 Pom. Eq., § 897.
1. Misjoinder of parties. The sub-contractors and attaching •creditors of E. M. & J. M. Brooks are proper parties to the bill. They have acquired liens on the fund, and their rights are so interwoven with those of the said contractors and with the contract that they can get no relief except-by an enforcement of the contract. This point is made more certain as to the extra pay for the raised work. Under the sub-contracts, this goes to the sub-contractors. A court of equity will allow all parties brought into one suit, that •equity may be fully meted out to each one. Besides it is alleged that each sub-contractor became the equitable owner of the amount ■due on his claim. The bill seeks to reach for them this amount ■and to enforce for them a statutory lien. Herrick v. Belknap, 27 Vt. 673.
2. Fraud in construction of contract.-
Courts of equity will relieve against fraud by the agents of railways in building contracts, the same as in other cases of fraud, and this, after the work is done. Canal Co. v. Pa. Coal' Co., 50 N. Y. 250; 1 Redfield Law of Ry. 443 ; Herriok v. Belknap, supra ; Banger v. By. Co., 5 H. L. Cas. 72, s. c. 27 Eng. L.. & Eq. 35.
The contractors were not bound to abandon the contract or rescind after discovering fraud, as they could not then be putin statu quo. Kerr on Fraud 330 : Gould v. Bank, 99 N. Y. 336; Krumm v. Beaeh, 96 lb. 406 ; Whitney v. Allaire, 1 lb. 305; Peek-v. Brewer, 48 111. 60 ; 24 Am. & Eng. Ry. Cas. 343.
It is objected that complainants sue for a quantum meruit. This is a technical phrase and only applies to a suit at law. In a court of equity it is immaterial what technical formalities are observed. The court will “ look through the shadow for the substance.” The proper measure of damages is the difference between the contract price and the actual cost of the work, and this is what we claim. Krumm v. Beaeh, 96 N. Y. 406; Dimmiek v. Loekwood, 10 Wend.. 155 ; Whitney v. Allaire, supra.
3. The contract is a legal one, but the fraud of the engineers-vitiates their action, and gives grouud for equitable relief. Where-the decisions of the engineer shows fraud, partiality, or incompetency, or that he is in collusion with either party, his estimates are-not binding, and the party defrauded is released from his supervision. B. B. Co. v. March, 114 U. S. 550 ; Sweeney v. TT. S.,. 109 lb. 620 ; Kihlberg v. U. S., 97 lb. 501 ; U. S. v. Bobeson, 9 Peters 327; Pierce on Railroads 382; 2 Story Eq. Jur., § 1457 a Hudson v. McCartney, 33 Wis. 342; Kistler v. B. B. Co., 88 Ind. 460; B. B. Co. v. Woods-, 14 Grat. 461; McMahon v. B. B. Co.,. 20 N. Y. 467 j 12 Am. & Eng. Ry. Cas. 317.
4. Extension of time. The company was bound to extend the-time in which to do the work, as the delays occurred because of its-own misconduct and fraud. B. B. Co. v. Donnegan, 34 Am. & Eng. Ry. Cas. 320. Such extension was expressly provided for-by the contract, and the failure of the company to extend the time was such a breach of the contract as released the contractors from obligation under it. The arbitrary action of the engineer in putting an extra force on the work forfeited the contract. 34 Am. & Eng. Ry. Cas. 122. The same is true because of the failure to-make proper monthly estimates and payments. Bugg v. 3Ioore, 1 Atl. Rep. 324 ; Reybold v. Voorhees, 37 Pa. St. 116 ; 2 Parsons’ Con. 522, 523; Merrill v. R. R. Co., 16 Wend. 588.
5. Measure of damages. Even if the contractors committed the breach of the contract, the company is bound to pay over all but the reserve fund of ten per. cent. This is liquidated damages and conclusive against the claims of both where the damages are uncertain and incapable of ascertainment, unless the amount is set aside by a court of equity as excessive. 24 Am. <& Eng. Ry. Cas. 349, note; 3 Parsons’ Con. 156 ; Foley v. McKeegan, 4 Iowa 1 ; Wolf v. Bes Moines, 64 lb. 380 ; Easton v. Canal Co., 13 Ohio 79; Pierce v. Jung, 10 Wis. 2Q;Farle v. Buck, 11 Pa. St. 469 ; Geiger v. R. R. Co., 41 Md. 4; Durnel v. Brown, 54 Me. 468 ;Herinessy v. Farrell, 4 Cush. 268 ;R. R. Co. v. Rust, 19 Fed. Rep. 239.