Milwaukee Boiler Co. v. Duncan

Milwaukee Boiler Company v. Duncan

Milwaukee Boiler Co. v. Duncan, 58 N.W. 232 (Wis. 1894)
Download
Format
Include

Star paging (*137) is kept for pin cites.

Court
Wisconsin Supreme Court · State Highest Courts
Decided
February 23, 1894
Judges
Pinney
Citations
58 N.W. 23287 Wis. 1201894 Wisc. LEXIS 141
Headnotes
Sale of chattels: Boiler manufactured to order: Warranties, express and implied: Waiver of breach: Duty to avoid enhancing damages. 1. Where a known, described, and defined article is ordered of a manufacturer, although it is stated to be required by the purchaser for a particular purpose, still, if the known, described, and defined thing be actually supplied, there is no warranty that it shall answer the particular purpose intended by tbe buyer. 2. If an article is sold by a formal written contract which is silent on the subject of warranty, no oral warranty made at the same time or px-eviouslj' can be shown; nor can any additional oral warranty be ingrafted or added to one that is written. 8. A contract to furnish a boiler “to be allowed 180 pounds of steam working pressure by United States inspectors,” does- not warrant that such boiler will produce or maintain a working pressure of that amount. 4. Where there was a difference of opinion among engineers and boiler makers as to how the grate hangers should be placed in the furnace, and the contract contained no specification on that subject, and they were placed according to a common and approved mode of construction, the buyer cannot complain because some other method ■was not adopted. 5. Where the buyer, when the boiler was delivered, saw that the grate hangers were placed too high, and they could easily have been changed at a trifling cost, and he assumed to make the change himself although the maker offered to do it, he cannot afterwards complain that they were wrongly placed. 6. If the boiler leaked, when tested before starting, to such an extent as to interfere with the making of steam or as to require a greater amount of fuel, or so as to occasion damage to the boiler, it was the duty of the buyer to have the leak stopped, and not to use the boiler in that condition, to his damage or to the damage of the boiler.
Summary
APPEAL from the Circuit Court for Brown County. The plaintiff, a manufacturer of steam boilers in Milwaukee, brought an action against the defendant, engaged in the foundry and-machine business at Ft. Howard, and the owner of one or more steam barges on the lakes, to recover $1,100 and interest for the last instalment of $6,500, the price of a marine boiler built and delivered by the plaintiff for the defendant under an express contract, to wit: “ John Duncan, Esq., Fort Howard, Wis.— Dear Sie: Inclosed please find duplicate contracts for marine boiler, which we hope will be satisfactory. If so, please accept, and return one to us. We have ordered the plate, and expect the steel mill will hurry it out for us. We guaranty the boiler to be a first-class job. Yours truly, “Milwaukee Boilee Go., “T. S. McGregor, Superintendent. “John Duncan, Esq., Fort Howard, Wis.— DeaR Sir: We propose to furnish you, F. O. B. cars here, March 1, 1891, sooner if possible, one fire box marine boiler, 10 ft. 6 in. by'16 ft. long, to be allowed 130 lbs. steam working-pressure by U. S. inspectors, to have two furnaces 58 in. high, 53 in. wide, 84 in. long, with one 10 and one 32 in. flue in each, large flues to have Adamson expansion joint, 156 4-in. tubes, 12 ft. 9 in. long. Steam drum, 54 in. by 8 ft. long, with two 15 in. by 12 in. nozzles, to be connected at Fort Howard. Shell of boiler, 70-100 in. thick; throat 70-100; balance of boiler outside % and -§■ thick,- — all of the best marine flange steel, 60,000 lbs. tensile, strength. Boiler to be tested to 195 lbs. water pressure, then steamed up and all leakage stopped before shipping. Ash pan, 15 ft. 6 in. x 26 x 8 in. x 3-16, connected, if necessary, at Fort Howard, breeching, and 20 ft. of 60-in. stack. Price, $6,500. “ Yours truly, Milwaukee BoileR Go., “ T. S. McGregor, Superintendent. “Terms of payment: $1,800, January 5, 1891; $1,800, February 5, 1891; $1,800, March 5, 1891; balance, $1,100, 90 days from date of shipment of boiler,— $6,500.” The defendant accepted the proposition, and a boiler was constructed of the material, kind, and size, in all respects, as specified in the contract, and was duly tested and placed in the defendant’s boat. The defense was (1) that the boiler leaked; (2) that it was not so built as to be allowed 130 pounds steam pressure by the government inspector, and would not maintain a working pressure of that amount; [3) that the grate hangers were placed too high in the furnace, and too near the bottom of the large flue, whereby the defendant was unable to maintain sufficient fire to get up sufficient steam. The grate bars were put in by the defendant. The boiler was inspected, and allowed to carry 100 pounds of steam, and finally 130 pounds. Evidence was given tending to show that the boiler leaked, and that by reason of the position of the grate the defendant could not get up enough steam, and generally in respect to the alleged defects in the boiler and their effect upon the capacity of the' boat. The court rejected evidence offered to prove that, pending the making of the contract, the defendant informed the plaintiff that he required a boiler that would produce 130 pounds of steam working pressure. Other rulings as to evidence are noticed in the opinion. The court, among other things, charged the jury that the boiler was to be a first-class job, but there was no warranty contained in the contract as to what this boiler would do,— what amount of steam could be produced by or in it. That if placing the grates on a level with the flue in boilers of this size and kind was a common and approved mode of construction, and there is simply a difference of opinion among engineers and boiler makers as to whether this or some other mode was best in boilers and furnaces of the size and construction called for by the contract, as the evidence tended to show, then it was not a violation of the contract that it adopted one method rather than another, the contract being silent upon the subject. If he had wanted one plan rather than another, it was his business to provide for it in the contract. That the law does not permit a party who has been damaged by the failure of another to perform his contract to so conduct himself or his business as to enhance the damages, and recover the enhanced damages. That if there were defects in the boiler, apparent, visible,.and known to the defendant, which could have been remedied, he had no right to use the boiler in that condition to his damage, and then charge it to the plaintiff. If the boiler leaked, when tested before starting, to such extent as to interfere with the making of steam or as to require a greater amount of fuel, or so as to occasion damage to the boiler, it was the defendant’s duty to have the leak stopped, and not to use the boiler in that condition, to his damage or to the- damage of the boiler. So as to the grates, — -if not in the right place, and that fact was apparent to the defendant, it was his duty to put them in the right place or position before using the boat. The court declined to charge that there was any implied warranty of the boiler,and said that “there is an express warranty here that the boiler should be a good and workmanlike job, so far as the construction and finish of it is concerned; but it had to be done in accordance with the specifications of the contract, and, if the result is that the boiler so constructed is unfit for the work for which the defendant wanted it, the plaintiff is not responsible for it; ” that “ if the boiler was made according to contract, and the contract was complied with in all particulars, the plaintiff was entitled to a verdict for $1,100 and interest from July 1, 1891.” The plaintiff had a verdict for the amount claimed, and from a judgment rendered against the defendant therefor, with costs, he has appealed.

Syllabus and headnotes are prepared by the reporter or publisher, not the court, and are not part of the opinion.

Opinion of the Court — Pinney

Text extracted by OCR from a scanned original; check the original for exact wording.

Pinney, J.

1. The clause in the contract, “ to be allowed 130 pounds of steam working pressure by United States inspectors,” was not an assurance that the boiler contracted for would produce and maintain a working pressure to that amount. It has no reference to the capacity of the boiler, and plainly refers to the government inspection of boilers under sec. 4418, R. S. of U. S., and that it would be such a boiler that they would permit a working pressure of 130 pounds, and set the safety valve accordingly. There was no express- warranty therefor beyond the guaranty that the boiler should be a first-class job.

2. The contract contains, it will be seen, very many definite specifications in respect to the construction of the boiler and the size and character of its several parts, and it has been found by the jury that the contract in these respects had been complied with by the plaintiff. The jury was instructed that, if the boiler was not a first-class job in the particulars of construction specified and complained of, there was a failure to perform the contract, and, if it had not been performed in these respects, the plaintiff was not entitled to the full contract price if the boiler Avas Avorth less for that reason. So, it Avill be seen that the jury have found against the contentions of the defendant in these respects.

3. It was made plain that the defendant got the exact article or thing he bargained for; and, although it may have been stated that it was required for a particular purpose, still, as he did not exact an express Avarranty, he took the risk of its fitness for the intended use, and no Avarranty in that respect can be implied. Benj. Sales, § 657; Chanter v. Hopkins, 4 Mees. & W. 399; Ollivant v. Bayley, 5 Q. B. 288. In Jones v. Just, L. R. 3 Q. B. 197, 202, the rule was laid down that “where a known, described, and defined article is ordered of a manufacturer, although it is stated to be required by the purchaser for a particular purpose, still, if the knoAvn, defined, and described thing be actually *125 supplied, there is no warranty that it shall answer the particular purpose intended by the buyer.” "Where the buyer in such case gets what he has bargained for, there is no implied warranty. Seitz v. Brewers' Ref. Co. 141 U. S. 518, 519 ; Goulds v. Brophy, 42 Minn. 109; Deming v. Foster, 42 N. H. 165. The distinction seems to be between the manufacture or supply of an article to satisfy a required purpose and the manufacture or supply of a specified, described, and defined article, as in this case. In the former case there may be an implied warranty, but in the latter there is none. It is equally well settled that, if the article is sold by a formal written contract which is silent on the subject of warranty, no oral warranty made at the same time or previously can be shown, as the writing is conclusively supposed to embody the whole contract; nor can any additional oral warranty be ingrafted or added to one that is written. Merriam v. Field, 24 Wis. 640 ; McQuaid v. Ross, 77 Wis. 470 ; De Witt v. Berry, 134 U. S. 312 . The ruling of the court in rejecting the evidence of McGregor, the tendency of which was to show a parol warranty or that the plaintiff knew for what use the boiler was required, was correct. The instructions of the court were in accordance with these principles, and fairly submitted to the jury the question in respect to the warranty or guaranty contained in the contract.

4. As there was no express warranty other than that stated in the contract as to finish and workmanship of the boiler, already noticed, and no warranty could be implied, the defendant has no reason to complain of the rejection of evidence bearing on the subject of damages in these respects. The claim that the grate hangers were placed too high was properly disposed of by the court, on the ground that it was a matter of opinion with machinists and engineers how high or low they should be placed, and the contract, though entering largely into details of construction, contained no specification on the subject. The defendant tes- *126 tilled that he had had experience as a machinist in and about steam engines and boilers for over fifty years, and had had a machine shop of his own for twenty-five or thirty years; that when the boiler came he saw the defect,— that the hangers ought to be eight inches lower than they were; that the expense of lowering them was trifling; and that he knew, if. put down eight inches, the boiler would make steam better, but he started his boat without making the change, and made no change thereafter. Al-thóugh the plaintiff offered to make it, yet the defendant assumed to make it himself. He has no cause of complaint in this respect.

5. Considerable testimony was given in respect to the leaking of the boiler, but we do not see that any was excluded that was competent and proper. Three witnesses testified, in substance, that when the boiler was inspected its leaks were of no consequence, and not more than all new boilers do leak at first. The plaintiff had no notice of this inspection, and was not represented when it occurred. Other tests were had, and there was evidence tending to show that the defendant’s failure to furnish the proper means of making these tests tended to strain and injure the boiler and cause it to leak, and it was used in the defendant’s boat a considerable time without any effort being made to stop the leaks. As the jury evidently found that the plaintiff properly performed its contract, that point having been fairly submitted to them, the defendant has no ground to complain. We think that the charge of the court on this subject was correct. 1 Suth. Dam. 148; Poposkey v. Munkwitz, 68 Wis. 331 .

As there are no other questions requiring attention, it follows from these views that the judgment should'be affirmed.

By the Court.— The judgment of the circuit court is affirmed.

How later courts describe this case

No later court has written an explanatory parenthetical about this case yet.

Cited by 18 cases

View all citing references →
1895: 11897: 11900: 11903: 21905: 11906: 11907: 21908: 11909: 11910: 11911: 11915: 11917: 21919: 11928: 118952026peak 1903 · 2

Citing references are not a citator: they show that a later opinion cites this case, not whether it followed, distinguished, or overruled it. Check negative history before relying on this case.

Authorities cited 6

DepthCaseCited by
Seitz v. Brewers' Refrigerating MacHine Co., 141 U.S. 510 (1891) 304
De Witt v. Berry, 134 U.S. 306 (1890) 97
Poposkey v. Munkwitz, 32 N.W. 35 (Wis. 1887) 40
Goulds v. Brophy, 6 L.R.A. 392 (Minn. 1889) 25
Merriam v. Field, 24 Wis. 640 (1869) 19
McQuaid v. Ross, 46 N.W. 892 (Wis. 1890) 5

Keyboard shortcuts

/Focus the search box
j kNext / previous result
EnterOpen the selected result
xAdd / remove the selected result from the download list
n pNext / previous search term in a case
cCopy the citation of the current case
+ −Larger / smaller reading text
?Show this list