TaiLexi AI U.S. Case Law

Electric Appliance Co. v. United States Fidelity & Guaranty Co.

The Electric Appliance Company v. The United States Fidelity & Guaranty Company, imp.

Elec. Appliance Co. v. United States Fid. & Guar. Co., 85 N.W. 648 (Wis. 1901)
Download
Format
Include

Star paging (*137) is kept for pin cites.

Court
Wisconsin Supreme Court · State Highest Courts
Decided
May 21, 1901
Judges
Bardeen
Citations
85 N.W. 648110 Wis. 4341901 Wisc. LEXIS 178
Disposition
Reversed.
Headnotes
Suretyship and guaranty: Municipal corporations: Liability for labor- ■ ers’ and materialmen’s claims: Waiver. 1, Where a contract with a city for the erection of a lighting plant expressly stipulated that the bond to be given by the contractor for the faithful performance thereof should also be conditioned for the payment by the contractor of all claims for material and labor, the acceptance of a bond without such condition embodied therein is a waiver thereof. 2. Statutes giving a mechanic’s lien do not extend to, and cannot be enforced against, the buildings and real estate of municipal corporations held for public use. 3. In such case where the contract provides that the plant shall be completed and ready for acceptance free and clear of all claims or liens for labor performed or material furnished, a materialman cannot maintain an action against a surety on a bond given by the contractor to the city for the faithful performance of his contract, the engagement of the surety being with the city and not with third persons. 4. To entitle a person to recover on an agreement between third persons there must not only be an intent to secure some benefit to him, but there must be a promise, legally enforceable. •5. Where a bond to secure a contract with a city for the erection and installation of a lighting plant was conditional for the faithful per- ■ formance of the contract, and the contract provided that, before final payment by the city, the contractor should present receipts in full for all labor performed and materials furnished in the construction and installation of the plant, no action can be maintained on such bond where full payment was made in violation of such express stipulation of the contract.
Summary
Appeal from an order of the circuit court for Dodge county: James J. Dick, Circuit Judge. The defendant The United States Fidelity dh Guaranty Oom-gczny has appealed from an order overruling a demurrer to the plaintiff’s complaint. The complaint was challenged on the ground that there was a defect of parties defendant, and •that it did not state facts sufficient to constitute a cause of action. It appears that the city of Waupun was desirous of erecting a municipal lighting plant. Rids were invited, and on September 2, 1899; a contract was entered into between the city and the defendants Rockwell & Snyder to erect the samej and have it fully completed and ready for delivery on or before November 15th of that year. The contract stipulated, among other things, that the plant should be delivered “free and clear of all claims or liens for labor performed or materials furnished or otherwise,” and that, before final payment should be made therefor or be deemed to be due on said contract, the contractors should present to the city receipts in full for all labor performed and materials furnished in and about the construction and installation of the plant. It also provided that the contractors should furnish a bond in the sum of $20,000, conditioned for the faithful performance of the contract on their part, and for the payment by them ot all claims for materials and labor. A bond was given by the defendant guaranty company conditioned that the contractors should “ well, truly, and faithfully comply with ail the terms, covenants, and conditions of said contract on their part to be kept and performed, according to its terms,” subject to certain provisions now to be stated: The city was to notify the surety, in writing, of any act on the part of the contractors under the contract, which might involve a loss for which the surety might become liable, immediately after the occurrence of such act shall have come to the city’s knowledge. In the event of a breach of any condition of the bond, the surety was to be subrogated to all rights of the contractors growing out of the contract, and all deferred payments or moneys thereafter to become due were to be credited upon any claim the city might make upon the surety because of such breach. Another condition was that the city should give the surety “ due notice before the last payment under the contract herein referred to is made to the principal; otherwise, this obligation shall be void as to any liability of the surety hereunder.” The complaint then sets out that, in order to carry out the contract, the contractors purchased merchandise and machinery of the plaintiff amounting to $2,396.19, which were used in the construction and equipment of the plant. The contractors have fully complied with the conditions of the contract on their part, except that they have not phid plaintiff’s demands and the claims of others. The city has accepted the plant and paid the contractors therefor. It is further alleged that the surety was duly notified by the city of the failure of the contractors to comply with the conditions of their contract as to the payments of said claim immediately after its breach, and immediately after the occurrence of such breach had come to the knowledge of the city, a copy of such notice being attached to the complaint. The prayer for relief is that plaintiff be subrogated to the rights of the city as against the other defendants, and for judgment against them for the amount of its claim. The bond in question runs to the city of Waupun and the state of Wisconsin, but, inasmuch as it does not appear that the state had any interest in the contract or any interest in the controversy, the case will be considered the same as though the state was not a party to such bond.

Syllabus and headnotes are prepared by the reporter or publisher, not the court, and are not part of the opinion.

Opinion of the Court — Bardeen

Text extracted by OCR from a scanned original; check the original for exact wording.

The following opinion was filed April 9, 1901:

Bardeen, J.

If any liability exists on the part of the guaranty company, it must rest upon the fact that it has contracted with the city to pay the debt due from the contractors to the plaintiff. The demand to be subrogated to the rights of the city as against the contractors has no foundation to rest upon, because it affirmatively appears that the city has accepted the plant and paid the contractors therefor. The city has no claim against the surety, because it has suffered no loss, and has sustained no injury, by reason of the failure of the contractors to pay the plaintiff’s claim. By reference to the contract, it will be seen that the contractors bound themselves to furnish a bond, not only for the faithful performance of the contract, but for the payment of all claims for labor and materials. The *438 bond accepted by the city omitted this latter provision, and was conditioned only for the performance of the contract. The contract was apparently drawn upon the theory that the city might be liable for the claims of laborers and ma-terialmen. Such, however, is not the fact. In Burnham v. Fond du Lac, 15 Wis. 193 , approved in Buffham v. Racine, 26 Wis. 449 , this court held that a municipal corporation was not subject to the process of garnishment. Basing it upon grounds of public policy, and as being in harmony with the rule just stated, this court, in Wilkinson v. Hoffman, 61 Wis. 637, held that statutes giving a mechanic’s-lien did not extend to, and could not be enforced against, the buildings and real estate of municipal corporations held for public use. The rule was further extended in Chapman V. Mfg. Co. v. Oconto W. Co. 89 Wis. 264 , by denying the' right to a lien upon the property of a water company organized for the purpose of and under contract with a city for furnishing its water supply. The fact that the city7- expressly contracted that the bond given should be for the payment of materialmen and. laborers, and then accepted a bond without such a condition, is clearly a waiver of that condition of the contract, and indicates an intention to abandon or relinquish its scheme in that respect.

But, it is urged, the contract says the plant shall be completed and ready for acceptance “ free and clear of all claims or liens for labor performed or material furnished or otherwise.” The plaintiff has a claim for material that has not been paid; hence there is a breach of the contract. Claims against whom ? certainly not against the plant, because the law says that no such claim can exist. Therefore there was no breach of the contract on any theory that plaintiff’s claim was one against the plant which the city was legally bound to discharge. Whatever may be the state of the law elsewhere, it is not believed that the cases in this jurisdiction will sustain the proposition that the third party can maim *439 tain an action against an alleged promisor based upon an implied promise to pay. The express promise, either by simple contract or covenant under seal, must exist. A few of the many cases in this state are as follows: Kimball v. Noyes, 17 Wis. 695 ; Putney v. Farnham, 27 Wis. 187 ; Kollock v. Parcher, 52 Wis. 393 ; Johannes v. Phenix Ins. Co. 66 Wis. 50 ; Nix v. Wiswell, 84 Wis. 334 ; Fulmer v. Wightman, 87 Wis. 573 ; Morgan v. South Milwaukee L. V. Co. 97 Wis. 275 ; Stites v. Thompson, 98 Wis. 329 .

The surety’s engagement in the bond was to pay to the city, and not to third parties. There are cases going to the limit of holding that, to entitle the third person to recover upon a contract made between other parties, there must not only be an intent to secure some benefit to such third person, but the contract must have been entered into directly and primarily for his benefit. Parker v. Jeffery, 26 Oreg. 186 . An exhaustive note on the general subject may be found in 25 L. R. A. 257 [Jefferson v. Asch], We consider the true rule to be that there must not only be an intent to secure some benefit to the third party, but there must be a promise, legally enforceable. The contract and bond in this case fail to meet these requirements. The situation presented shows a want of any intent to secure a benefit to third parties. When the city accepted a bond that did not attempt to secure the payment of materialmen, and which provided that the surety should be subrogated to the rights of the city in case of a breach and be entitled to credit on the claim of the city for all payments due the contractors thereafter. to become due, this was inconsistent with the theory that it was the rights of third parties that were being secured.

There is, however, another branch of this case fatal to the plaintiff’s alleged cause of action. The contract provided that, before the final payment should be made by the city or be deemed to be due, the contractors should present *440 receipts in full for all labor performed and materials furnished in the construction and installation of the plant. The complaint alleges that the contractors fully complied with the conditions of the contract, except the payment of plaintiff’s claim and the claims of others, and that the city duly accepted the plant and paid the contractors therefor. No provision in the contract required any payment of the contract price until the work was completed and accepted. The city paid the contractors in full for the plant, and the inference is irresistible that such payment was made in defiance to the express terms of the contract that it should not be made until receipts in full had been produced. As said in W. W. Kimball Co. v. Baker, 62 Wis. 529 : “It is elementary that sureties are favorites in the law, and have a right to stand upon the strict terms of their obligations when ascertained. Beyond the burdens thus taken upon themselves they are not bound.” So far as anything appears in the complaint, the city had the entire contract price in its possession when the alleged notice was given. The surety had a right to rely upon the fact that the city would hold the contractors to strict ■ fulfillment of their obligations. Any variance therefrom to the prejudice of the surety would work a discharge. This is elementary. That this stipulation was of importance to the surety admits of no doubt. That it was broken by the city is certain. No successful attempt can be made to resolve the undertaking of the surety into different factors, and say that they are independent, and one subsists for the benefit of this plaintiff, and another may fail because of the conduct of the assured. So far as this case is concerned, the obligation of the surety is a unit, and no liability can be predicated thereon except in accordance with the terms of the contract. This is not shown by the complaint, and hence this action cannot be maintained.

Our attention has been directed to several cases in Ne *441 braska apparently sustaining the plaintiff’s contentions. They go far beyond any case to be found in this court, and are based on premises we do not care to adopt. The case of Baker & Co. v. Bryan, 64 Iowa, 561 , also cited by plaintiff, shows that the engagement of the sureties was that the contractor should “pay all claims for material, labor,” etc. The court was of the opinion that the contract and bond indicated an intent to secure all persons furnishing labor and materials to be used in the construction of the building, and therefore .held the sureties liable. ¥e have arrived at the conclusion that the contract and bond in suit do not disclose an intent to secure third parties. ¥e deem it clear, under the circumstances, that the bond was taken for the city’s benefit, and this conclusion is amply confirmed by the practical construction given it by the parties. .

By the Court.— The order appealed from is reversed, and the cause is remanded with directions to sustain the demurrer to the complaint and for further proceedings according to law.

A motion for a rehearing was denied May 21, 1901.

How later courts describe this case

No later court has written an explanatory parenthetical about this case yet.

Cited by 44 cases

View all citing references →
1901: 11904: 11905: 11906: 21907: 11908: 21909: 11912: 11913: 21914: 11915: 11916: 21917: 21919: 21920: 31924: 21926: 31928: 21931: 31932: 31934: 11935: 11941: 11949: 11957: 11966: 11967: 12004: 119012026peak 1920 · 3

Relies on it most ⓘ

  1. Smith v. Bowman88 P. 687 (Utah 1907)
  2. Concrete Steel Co. v. Illinois Surety Co.157 N.W. 543 (Wis. 1916)
  3. Northwestern Bridge & Iron Co. v. Maryland Casualty Co.177 N.W. 31 (Wis. 1920)
  4. Silver King Coalition Mines Co. of Nevada v. Silver King Consol. Mining Co. of Utah204 F. 166 (8th Cir. 1913)
  5. Knight & Jillson Co. v. Castle87 N.E. 976 (Ind. 1909)
  6. Conold v. Stern35 N.E.2d 133 (Ohio 1941)

Most recent

  1. Ruskin A. Vest, Jr. v. Duncan-Williams, Inc.No. M2003-02690-COA-R3-CV (Tenn. Ct. App. May 4, 2004)
  2. Peters v. Peters Auto Sales, Inc.155 N.W.2d 85 (Wis. 1967)
  3. Winnebago Homes, Inc. v. Sheldon139 N.W.2d 606 (Wis. 1966)
  4. Bourrett v. W. M. Bride Construction Co.84 N.W.2d 4 (Iowa 1957)
  5. State Department of Public Welfare v. Schmidt39 N.W.2d 392 (Wis. 1949)
  6. Conold v. Stern35 N.E.2d 133 (Ohio 1941)

Citing references are not a citator: they show that a later opinion cites this case, not whether it followed, distinguished, or overruled it. Check negative history before relying on this case.

Authorities cited 14

DepthCaseCited by
Baker & Co. v. Bryan, 21 N.W. 83 (Iowa 1884) 49
Parker v. Jeffery, 37 P. 712 (Or. 1894) 48
Putney v. Farnham, 27 Wis. 187 (1870) 45
Johannes v. Phenix Ins. Co. of Brooklyn, 27 N.W. 414 (Wis. 1886) 36
Burnham v. City of Fond du Lac, 15 Wis. 193 (1862) 28
Kollock v. Parcher, 9 N.W. 67 (Wis. 1881) 26
Buffham v. City of Racine, 26 Wis. 449 (1870) 18
Wilkinson v. Hoffman, 21 N.W. 816 (Wis. 1884) 18
Chapman Valve Mfg. Co. v. Oconto Water Co., 60 N.W. 1004 (Wis. 1895) 15
Morgan v. South Milwaukee Lake View Co., 72 N.W. 872 (Wis. 1897) 14
Nixv v. Wiswell, 54 N.W. 620 (Wis. 1893) 13
Stites v. Thompson, 73 N.W. 774 (Wis. 1898) 13
Kimball v. Noyes, 17 Wis. 695 (1864) 12
Fulmer v. Wightman, 58 N.W. 1106 (Wis. 1894) 3

Keyboard shortcuts

/Focus the search box
j kNext / previous result
EnterOpen the selected result
xAdd / remove the selected result from the download list
n pNext / previous search term in a case
cCopy the citation of the current case
+ −Larger / smaller reading text
?Show this list