J. E. Hathaway & Co. v. United States

J. E. Hathaway & Company v. United States

J. E. Hathaway & Co. v. United States, 249 U.S. 460 (1919)
Download
Format
Include

Star paging (*137) is kept for pin cites.

Court
Supreme Court of the United States
Decided
April 14, 1919
Docket
No. 255
Judges
Brandeis
Citations
249 U.S. 46039 S. Ct. 34663 L. Ed. 7071919 U.S. LEXIS 2104
Syllabus
A finding by the Court of Claims that a delay by the Government in. approving a contract was reasonable is a finding of ultimate fact, binding upon this court unless made without evidence or inconsistent with other facts found. ■ P. 463. Quaere: Whether unreasonable delay on the part of the Government in approving a contract can entitle the contractor to an extension where the contract fixes a definite date for completion of the work? Id. District of Columbia v. Camden Iron Works, LSI U. 8; 453, distinguished. A provision for deducting, in addition to an amount fixed as liquidated. damages, the expense of superintendence and inspection, in case of failure to complete the work by the time specified, will be enforced when clearly expressed in the contract. P. 464. A contention that sufficient credit of time was not allowed by the Government to the contractor for extra work held not reviewable in this court, it not having been made in the Court of Claims. Id.
Summary
APPEAL PROM THE COURT OP CLAIMS. The case is stated in the opinion. Here was a month taken, at the best season of the year for working, simply to obtain - record evidence of the authority of the attorney in fact of the surety company to sign the contract. The delay was wholly on the part of the Government. . "Whether styled “reasonable” or “unreasonable,” it was a delay for which the contractor was in no degree responsible. That the delay in signing the contract on the part of the Government was reasonable is, it is submitted, not a finding of fact but a conclusion of law. United States v. Pugh, 99 U. S. 265; Sun Insurance Co. v. Ocean Insurance Co., 107 IT. S. 485, 502, 503. Such a conclusion embodied in the findings of fact is not binding in this court. "When the contract was signed by the contractor and the bond executed by a surety company, the contractor had done everything which he could do to enter into a legally binding contract with the Government. To supply the slight defect a telegram should have been sent to the contractor. The injustice of holding this contractor to a date of completion offered by him on April 29, when he was not notified of the completion of the contract as a binding obligation of the Government until June 13, is apparent. As soon as the contractor made his bid April 29, 1910, he was bound. United States v. Porto Rico S. S. Co., 239 U. S. 88. He was not notified that the contract was awarded to him until May 11, twelve days thereafter. There is no explanation of this delay and no apparent reason for it. District of Columbia v. Camden Iron Works, 181 U-. S. 453, is directly in point. See also American Dredging Co. v. United States, 49,,Ct. Clms. 350; Ittner v. United States, 43 Ct. Clms. 336; Little Falls Knitting Mill Co. v. United States, 44 Ct. Clms. 1; Callahan Construction Co. v. United States, 47 Ct. Clms. 229, 235, 236; Laidlaw-Dunn-Gordon Go. v. United States, 47 Ct. Clms. 271; Missouri Valley Bridge & Iron Co., 19 Comp. Dec. 712.

Syllabus and headnotes are prepared by the reporter or publisher, not the court, and are not part of the opinion.

Opinion — Brandeis

Mr. Justice Brandéis delivered the opinion of the court.

The United States solicited sealed proposals .for the repair of a revetment in Michigan; and J. E. Hathaway & Company became the successful bidders. Under a contract, dated May 11, 1910, they agreed to complete the work by December 1, 1910. It was not completed until 68 days later. Of this delay the Government conceded that 29 days were attributable to extra work required by it, and 10 more days were not counted against the contractor, being Sundays and holidays. For the remaining 29 days’ delay the Government deducted from the contract price $3082; claiming that amount under the provisions for liquidated and other damages. To recover the amount disallowed, J. E. Hathaway & Company brought suit in the Court of *463 Claims, which denied them relief (52 Ct. Clms. 267); and the case comes here on appeal.

First.

Claimants contend that they were entitled to an extension of more than these 29 days’ time for completing the work; because the contract and fcycnd were delivered by them to the Government May "18, duly executed, but were not approved by the Chief of Engineers until June 9, and notice of approval was not given them until June 13. The origin of this delay was the failure of the surety company to file with the War Department a copy of the vote of its directors giving him who signed the bond as attorney in fact authority so to do. -But claimants insist that this omission could have been quickly supplied, if the Government had telegraphed for a copy of the vote, and that practically all the delay was due to its unreasonable failure so to do.

The Court of Claims found: ' ‘ There was no unreasonable-delay on the part of the Government in approving the contract.” This finding, like one of reasonable value, Talbert v. United States, 155 U. S. 45, 46 , is a finding of an ultimate fact by which this court is bound, unless it appears that the finding was made without supporting evidence, Cramp & Sons Co.

v. United States, 239 U. S. 221, 232 ;

Stone v. United States, 164 U. S. 380 ;

United States v. Clark, 96 U. S. 37 , or is inconsistent with other facts found, United States v. Berdan FireArms Co., 156 U. S. 552, 573 . There is no such lack of supporting evidence or inconsistency here. We have consequently no occasion to determine whether, as was held in American Dredging Co.

v. United States, 49 Ct. Clms. 350, unreasonable delay on the part qf the Government. in approving a contract for an accepted bid can entitle the contractor to a corresponding extension of time, where a definite date is fixed by the contract for completion of the work. Compare Monroe v. United States, 184 U. S. 524 . The case of District of Columbia *464 v. Camden Iron Works, 181 U. S. 453, 461 , strongly' relied upon by claimants, is clearly distinguishable. There the contract, as interpreted by the court, provided that the work should be completed, not (as here) by a date fixed, but within a certain number of days; and the number of, days was to be'measured, not from the date of the contract but from J‘ the date of the execution of the contract.” What was there-decided is merely that under such circumstances it may be “shown that a deed, bond or other instrument was in fact made, executed and delivered at a date subsequent to that stated on its face.”

Second.

Claimants contend also that the Court of Claims erred in allowing, in addition to the sum of $100 a day as liquidated damages, the sum of $182 for the expense of superintendence and inspection. But the contract expressly provided that time should be deemed of the essence and that in case of failure to complete within the time specified “the contractor shall pay, in addition to the liquidated damages hereinbefore specified, all expenses for inspection and superintendence.” There is no reason why parties competent to contract may not agree that cei’tain elements of damage difficult to estimate shall be covered by a provision for liquidated damages and that other elements shall be ascertained in the usual manner. - Provisions of a- contract clearly expressed do not cease to be binding upon the parties, because they relate to the measure of damages.

Wise v. United States, ante, 361.

Third.

Claimants further contend that the credit of tune allowed by the Government on account of the extra work should have been greater. On this matter no issue appears to have been raised below; and it is obviously not open for review here.

The judgment of the Court of Claims is Affirmed.

How later courts describe this case

Explanatory parentheticals written by citing courts — 1 in all; the most informative distinct ones are shown.

Cited by 15 cases

View all citing references →
1923: 11924: 11933: 11934: 21941: 11973: 21978: 11982: 11996: 12004: 12006: 12007: 12022: 119232026peak 1934 · 2

Relies on it most ⓘ

  1. DHM Industries, Inc. v. Central Port Warehouse, Inc.318 A.2d 20 (N.J. Super. Ct. App. Div. 1973)
  2. HILLSBOROUGH CTY. AVIATION A. v. Cone Bros. Contr. Co.285 So. 2d 619 (Fla. Dist. Ct. App. 1973)
  3. Wechsler v. Hunt Health Systems, Ltd.330 F. Supp. 2d 383 (S.D.N.Y. 2004)
  4. Order of United Commercial Travelers v. Shane64 F.2d 55 (8th Cir. 1933)
  5. Dj Manufacturing Corporation v. United States86 F.3d 1130 (Fed. Cir. 1996)
  6. Burns v. Hanover Insurance454 A.2d 325 (D.C. 1982)

Most recent

  1. New Milford v. Standard Demolition Services, Inc.212 Conn. App. 30 (2022)
  2. Creative Waste Management, Inc. v. Capitol Environmental Services, Inc.495 F. Supp. 2d 353 (S.D.N.Y. 2007)
  3. Northwestern Mutual Life Insurance v. Uniondale Realty Associates11 Misc. 3d 980 (N.Y. Sup. Ct. 2006)
  4. Wechsler v. Hunt Health Systems, Ltd.330 F. Supp. 2d 383 (S.D.N.Y. 2004)
  5. Dj Manufacturing Corporation v. United States86 F.3d 1130 (Fed. Cir. 1996)
  6. Burns v. Hanover Insurance454 A.2d 325 (D.C. 1982)

Citing references are not a citator: they show that a later opinion cites this case, not whether it followed, distinguished, or overruled it. Check negative history before relying on this case.

Authorities cited 7

DepthCaseCited by
United States v. Berdan Fire-Arms Mfg. Co., 156 U.S. 552 (1895) 63
United States v. Clark, 96 U.S. 37 (1878) 55
Dist. of Columbia v. Camden Iron Works, 181 U.S. 453 (1901) 44
Stone v. United States, 164 U.S. 380 (1896) 41
William Cramp & Sons Ship & Engine Bldg. Co. v. United States, 239 U.S. 221 (1915) 25
Monroe v. United States, 184 U.S. 524 (1902) 23
Talbert v. United States, 155 U.S. 45 (1894) 7

Keyboard shortcuts

/Focus the search box
j kNext / previous result
EnterOpen the selected result
xAdd / remove the selected result from the download list
n pNext / previous search term in a case
cCopy the citation of the current case
+ −Larger / smaller reading text
?Show this list