Evans & Howard Fire Brick Co. v. National Surety Co.

EVANS & HOWARD FIRE BRICK COMPANY v. NATIONAL SURETY COMPANY

Evans & Howard Fire Brick Co. v. Nat'l Sur. Co., 173 N.W. 448 (S.D. 1919)
Download
Format
Include

Star paging (*137) is kept for pin cites.

Court
South Dakota Supreme Court · State Highest Courts
Decided
June 24, 1919
Docket
No. File No. 4515
Judges
Smith, Whiting
Citations
173 N.W. 44842 S.D. 1091919 S.D. LEXIS 94
Disposition
Affirmed.
Headnotes
1. Municipal Corporations — Suretyship—City Sewerage Construction —Company’s Surety re Labor and Materials — Indemnity, Whether Solely for City — Ultra Vires. A surety company’s contract with a construction company which was about to construct a city sewer was conditioned that construction company “shall assume' the defense of and indemnify and save harmless the city of * * * from all claims relating to labor and materials furnished under such contract * * * and shall also pay for all labor performed and materials used,” etc. Held, that, if the surety contract was intended to be for use and benefit of laborers and materialmen as well as the city itself — that is if such company contracted and agreed to become liable for and to. pay for labor and material entering into the sewer, in case the contractor failed to pay therefor, then no question of ultra vires,' involved in the objection that the city had no power to contract fo.r use and benefit of laborers and materialmen, arises. 2. Same — Surety Company’s Bight to Contract to Pay Laborers and Materialmen — Latter’s Bights re Such Contract — Consideration, Sufficiency of. A contractor for erection of a city sewer had the right, for his own benefit, to contract with defendant Guaranty Company, whereby the latter might obligate itself to pay laborers and materialmen, if the contractor should fail to pay, even in absence of a bond for protection of the city; and laborers or material-men for whose benefit such bond might be given though not named therein, could accept the contract so tendered by Guaranty Company, and become parties thereto, with a right of action thereon, in case contractor defaulted in his payments; nor would such laborers and materialmen be affected by the fact that the contract also indemnified the city against claim of laborers and materialmen; the question then being, not whether the city might contract for beifefit of such third persons, but whether the contractor and the Guaranty Company have entered into a contract for their protection. So held, where the bond was paid for by the contractor; such payment being sufficient consideration, even though such third persons were not cognizant of the existence of the contract. 3. Suretyship — City Sewerage Construction — Construction ■ Company’s Surety re Laborers and Materialmen — Indemnity—Materialman Unnamed in Contract, Bights Of. Under a contract of indemnity between a contractor for construction of a city sewer and a surety company, conditioned that if the contractor, “Shall assume the defense of and indemnify and save harmless the city of * * * from all claims relating to labor and materials furnished under such contract * * * and shall also pay for all labor performed and materials used or furnished,” etc., it appearing that plaintiff materialman accepted and relied upon such bond, held, as against the objection that the bond was given solely for protection of the city and not for benefit of labdrers and materialmen, that persons for whose benefit such a .contract is made need not be named therein; the general rule being that where contracts are evidently part of the same transaction, .persons becoming parties to one of such contracts, which provides for the other, is bound by the terms of both, 4. Same — Guaranty-City Sewerage Contract — Payment for Gabor and Material, Guarantor’s Obligation Equal to Contractors— Privity of Contract, Whether Necessary — Statute. The guarantor of a contract, such as that 'for construction of a city sewer, binds himself to performance of the same acts the principal himself has undertaken to perform; therefore, where a contractor expressly agreed to pay ail claims for labor and material, the guarantor 'binds himself to pay therefor equally with contractor; and laborers and material men may adopt such guaranty and enforce it, the same as though made directly to them; and while under the general rule there must be privity of contract 'between the parties, yet in-this state it is settled by the Rev, Code 1903, Sec, 1192 (Sec, 808 Rev, Code 1919), which provides that a contract made expressly for benefit of a third person may be enforced by him at any time before the parties thereto rescind it, 5. Same — Guaranty--City Sewerage Construction — Contractor’s Surety Bond, Recital of Obligation to Furnish Material and Baber, Effect re Contract with City — Contract with City— Contractor’s Obligations, Enumerated, Construed. Where a contract between .a construction company, and a city, for construction of a city sewer, contained no express agreement by construction company to pay for labor and materials used in such construction, but the surety’s bond with contractor recites that construction company has contracted with the city to furnish labor and material therefor, and is conditioned that the construction company “shall assume the defense of and indemnify and save harmless the city of * * * from all claims relating to labor and materials furnished,” etc., and shall hold said city harmless” against all claims fo? damages whatsoever arising for injury to persons or -property done in the prosecution of the work under said contract”; “shall also pay for all labor performed or material furnished,” etc., held, that the provisions of the bond guarantee that contractor will do four things: (1) construct the sewer according to -plans and specifications; (2) that contractor shall assume defense of and indemnify and save harmless the city from all claims relating to labor and materials furnished; (3) hold the city harmless against all claims for damages whatsoever arising from injury to persons or property done in prosecution of the work under the contract; and (4) that the contractor shall pay for all labor performed or materials used or furnished in carrying out the contract; the first three of which conditions are specifically and directly for benefit and protection of the city, while claims of laborers and materialmen are referred to, (11 in that the city is to be indemnified against such claims, (2) in that such claims are to be paid; under which latter head the benefit is directly for laborers and materialmen, and only indirectly for that of the city. 6. Mechanics’ Liens — Laborers’, Materialmens’, Lien, Upon Public Corporation Moneys, Construed — Statutes. Laborers and materialmen, upon complying with the statutes of this state, may acquire a lien u-pon moneys due or to become due contractor for construction or repair of any work for any county or municipality or public school corporation; construing Laws 1895, Ch. 135, Sec. 1, Code Civ. Proc. 1903, Sec. 713 (Sec. 1660, Rev. Code 1919). 7. Municipal Corporations — Guaranty—City Sewer Construction— Contractor’s Surety, Whether Indemnity to Materialmen — Indemnity Contract Interpreted — Materialman's Reliance on Bond, Effect. In view of the rulings established by decisions of this court, Sioux Falls Pressed Brick Co., v. Board of Education, 25 S. D. 36, 125 N. W. 291, Grant County v. McGowan Lumber Co., 41 S. D. 172 N. W., to the effect that where contractor had defaulted in payment for a portion of the work completed which did not become due contractor until final completion of the contract, did not become subject to liens of laborers or materialmen under said statute, and that moneys thus retained in hands of the public corporation might be used by them in completing the contract, — held, that if the contractor’s indemnity contract must be construed as indemnity for benefit of the city alone, the objection that the effect of the rule so laid down would be to enlarge the liability beyond that for the city’s benefit; would be insuperable; whereas, if it appears from the terms and express conditions of the bond that it was intended for protection of both the city and laborers and materialmen, such objection is without force; and therefore, held, further, that a surety bond given to a city in view of the construction by contractors of a sewer, which is conditioned that the surety company “shall assume the defense and indemnify and save harmless, the city of * * * from all claims relating to labor and materials furnished under such contract * * * and shall also pay for all labor performed and materials used or furnished in the carrying out of said contract,” is one made expressly for protection of laborers and materialmen, as well as the city; this notwithstanding the objection of surety company that the bond was given solely for protection of the city and not for benefit of laborers and materialmen, and that a surety cannot be held beyond express terms of his contract; the complaint -alleging that plaintiff materialman, in furnishing the materials, accepted and relied upon said bond. Whiting, J., concurring specially.
Summary
A-ppeal from -Circuit Court, Codington County. Hon. AViluiam -N. Skinner, Judge. Action -by Evans & Howard -Eire Brick Company, a corporation, against the National Surety Company, a corporation, to recover upon a contractor’s surety bond. From an order overruling a demurrer to the complaint, defendant appeals. (3) To point three of the opinion, Appellant cited; Lawrence v. Fox, 20 N. Y. 268; Lyth et al v. Kingston, 43 N. Y. S. 653, 14 A-pp. -Div. 11; Buffalo Cement v. McNaughton et al, 90 Hun. 74; Edward J. McCabe -Co. v. Luke A. Burke & Sons Co., 'Inc., (New York Law Journal, April 5, 1917); Eastern -Steel -Co., against Globe Indemnity Co. et al, Supreme Court New York County, New York Law Journal,'February 14, 1918, affirmed by Appellate Division (New York Law Journal, January 10, 1919) ; Jefferson v. Asch, 55. N. AY. 604; Kansas City 'S'ewer Pipe Co. v. Thompson, 25 S. AY., 522. Respondent cited - McQuillan Municipal Corporations, Sec. i960; Lyth v. Hingston, 43 N. Y. S. 653-, 14 App. Div. it; Park Brothers & Co. v. Sykes, 67 Minn. 153, 69 N. AY. 712; Lenz v. Chicago & N. AY. Ry. 'Co. (AVis.) 86 N. AY. 609; R. Connor Co. v. Olson (AVis.) 115- N. AY 811; Sec. 830 (485), pages 1266-1267, Dillon on Municipal Corpoations (5th Ed.)-, note 2; Parker v. Jeffrey, 26 Or. 186, 37 Pac. 712; Electric Appliance Co. v. United States Fid. & G. Co., no AVis. 434, 85. N. AY. 648, 53 L. R. A. 609; Fry v. A-usman, 29 S. D. 30, 1-3*5 N. AY. 708; Fisk & Hunter Co. v. New England Homestalee Co., 27 S. D. 221, 130 -N. AY. 841.

Syllabus and headnotes are prepared by the reporter or publisher, not the court, and are not part of the opinion.

Opinion of the Court — Smith

Text extracted by OCR from a scanned original; check the original for exact wording.

SMITH, P. J.

Appeal from an order overruling defendant’s demurrer to plaintiff’s complaint. The allegations of the complaint, so far as material to this appeal, are substantially as follows ;

*114 That on August 23, 1915, the Offerman Construction Company entered into a contract with the city of Watertown for the construction of certain sanitary sewers. That, as a condition precedent to awarding said contract, the ctiy of Watertown required said contractor to give a bond which was furnished by the National -Surety Company, defendant and appellant, and contained the following recitals and conditions:

“That we, Offerman Construction Company, a corporation of Omaha, Neb., principal, and National Surety Company of New York, as surety, are held and firmly bound unto the city of Watertown, South Dakota, a municipal corporation in the sum of $ro,ooo * * * for the payment of which well and truly to be made we hereby bind ourselves, etc. The condition of the foregoing obligation is such that, if the a'bove-bounden Offerman Construction Company * * * shall assume the defense of and indemnify and save harmless the city of Watertown * * * from all claims relating to- labor and materials furnished under such contract, * * * and shall also pay for all labor performed and materials used or furnished in the carrying out of said contract: Then-this obligation to be null and void; otherwise to remain in full force and effect and virtue.”

That said bond was accepted by said city, and in reliance thereon plaintiff furnished to the Offerman Construction Company materials (described) to the aggregate sum and value of $1,846.28, which materials were used by said company in the construction of said sewers pursuant to its contract. That the Offerman Construction Company became and was adjudged bankrupt on April 2, 1918, and never paid plaintiff for said material. That on July 8, 1918, plaintiff demanded of defendant surety company payment of the sum due for said materials so used, but that defendant refused and still refuses to pay the same or any part thereof, and denies its liability on said bond ■upon the ground that it is “not liable to labor and materials claimants.”

Two other causes of action similar in every respect are set forth in plaintiff’s complaint. Demurrer to the complaint on the ground that it does not state facts sufficient to constitute a cause of action. Demurrer overruled, and defendant appeals.

*115

[1] Appellant contends: First, that the city of Watertown was without power to enter into a contract for the use and benefit of third persons, viz., laborers and materialmen; second, that the contract of indemnity in this case was for the sole use- and benefit of the city; that laborers and materialmen are not, and were not intended to become, parties thereto, and cannot maintain this action.

In response to the first contention, it is sufficient to observe that, if the contract was clearly intended to be for the use and benefit of laborers and materialmen as well as the city itself- — in other words, if the defendant guaranty company contracted and agreed to become liable for and to pay for labor and material entering into the sewer in case the contractor failed to pay therefor ■ — no question of ultra vires arises.

[2] The contractor had the right, for its- own benefit, to enter- into a contract with the defendant guaranty company; whereby the guaranty company might obligate'itself to pay laborers and) materialmen, if it should fail to pay, even in the absence of any bond for the protection of the city, and clearly laborers or materialmen for whose benefit such bond might be given, even though, not named therein, could accept the contract thus tendered by the guaranty company, and become parties thereto with a right of action thereon in case the contractor defaulted in his payments. The rights acquired by laborers and materialmen under such a contract would not foe affected by the fact that the same contract also indemnified the city against claim-s of laborers and materialmen. The question then would seem to be, not whether the city might enter into a contract for the benefit of third persons, to wit, laborers and materialmen, but whether the contractor and the guaranty company -have entered into-a contract for their protection. The consideration for the bond was paid, not by the city of Watertown, but by the contractor. Such payment would constitute a sufficient' consideration, even though 'third persons for whose benefit such- bond may have been given were not named as parties thereto, nor even cognizant of its existence, and such persons by adopting the promise made for- their benefit could bring themselves into privity with the promisor and enforce the promise as though made directly to them. Thorp. v. Keokuk Coal Co., 48 N. Y. 257 ; Clark v. Howard, 150 N. Y. 238 , 44 N. E. 695 .

*116

[3,4] Whether the provisions of the bond in this case entitle laborers and materialmen to accept and become privies thereto presents a question of much greater difficulty. The complaint alleges that plaintiff accepted and relied upon the bond. It is appellant’s contention, however, that the bond, on its face and by all its provisions, discloses that it was given solely for the protection of the city, and not for the benefit of laborers and material-men; that a surety cannot be held beyond the express terms of his contract.

In Fish & H. v. N. E. H. Co., 27 S. D. 221, 130 N. W. 841 , this court held that persons for whose benefit a contract of this kind is made need not be named therein. In Fry v. Ausman, 29 S. D. 30; 135 N. W. 708 , 39 L. R. A. (N S.) 150, Ann. Cas. 1914C, 842, it was held that—

“Recovery can only be had in case the contract was ‘made expressly for the benefit of a third person.’ ”

In Chung Kee v. Davidson, 73 Cal. 522 , 15 Pac. 100 , the court held that—

“It must appear, however, by the direct. terms of the contract, that it was made for the benefit of such parties. It cannot be implied from the fact that the contract would, if carried out between the parties to it, operate incidentally to their benefit.’

The general rule is that — ■

“Where contracts are evidently part of the same transaction, a person who beomes a party to one of such contracts which provides for the other is bound by the terms of both.” 13 C. J. 713, § 821.

That is, the guarantor of a contract binds himself to a performance of the same acts which the principal himself has undertaken to perform. Therefore where a contractor, by the terms of his contract, has expressly agreed to pay all claims for labor and material, the guarantor binds himself to pay for such labor and material equally with the contractor, and laborers and materialmen may adopt such guaranty and enforce it the same as though made directly to them. Jordan v. Kavanaugh, 63 Iowa, 152 , 18 N. W. 831 . The general rule undoubtedly is that to sustain an action there must be privity of contract between the parties, though in many jurisdictions it is held, even in the absence of statutory provision, that, if one person makes a promise to another upon a *117 consideration for the benefit of a third party, the latter may maintain an action upon it, though the consideration did not move from him. The conflict of decisions, however, appears irreconcilable upon principle. In this state it is settled by section 1192, Revised Code 1903 (section 808, Code 1919), which provides:

“A contract, made expressly for the benefit of a third person, may be enforced by 'him' at any time before the parties thereto rescind it.”

No -question of rescission is involved in this case. The interpretation of the section is not free from difficulty. It appears to be a legislative recognition and adoption of the rule which seems to be sustained by the weight of authority. But the reasons announced in different jurisdictions are so diverse as to give rise to more or less difficulty in its application'. In some states in which it has been adopted by -decisions, it is held inapplicable to a contract -which is purely conditional and contains no express promise for the benefit of the third party. -Chung Kee v. Davidson, 73 Cal. 522 , 15 Pac. 100 .

The California court, interpreting the section of their Code which is identical with our statute, said:

“We cannot say that the contract before us was made expressly for the benefit of the plaintiffs’ assignors. O-n the contrary, we think it was made expressly for the benefit of the parties named therein. The most that can be said is that it is a contract incidentally for the -benefit of those who worked in the mine. * * * It is not necessary that the party for whose benefit the contract has been made should be named in the contract. It must appear, however, by direct terms of the contract, that it was made for the benefit of such parties. It cannot 'be implied from the fact that the contract would, if carried out between the parties to it, operate incidentally to their benefit.”

In the case of Electric Appliance Co., v. U. S. Eidelity & Guaranty Co., no Wis. 434, 85 N. W. 648 , 53 D. R. A. 609, the court said:

“We consider the true rule to be that there must not only •be an intent to secure some benefit to the third.party, but there must be a promise legally enforceable.”

In that case the contract guaranteed provided that the plant should be completed and ready for acceptance free and clear of *118 all claims or liens for labor performed or material furnished or otherwise. The contract guaranteed, however, contained no provision expressly -obligating the contractors to pay claims of laborers and materialmen, and the court held that the sole agreement in the bond was to indemnify the city and not to pay third parties.

In the case of Parker v. Jeffery, 26 Or. 186 , 37 Pac. 712 , a firm contracted with the city of Portland) to furnish material and perform labor necessary for the construction of a sewer. .In the contract the contractors expressly agreed that they “would' pay. all sums of money due at the completion of the work, or hereafter to become due, for material used in and labor performed on or in connection with said work.”

■Defendants executed a guaranty bond conditioned that—

“Whereas, the above-bounden Robertson Bros, have this dav entered into a contract with the city of Portland for the construction of a sewer. * * * Now, if said contractor- shall well and faithfully perform all the covenants and conditions in said contract mentioned, then this obligation to be void; otherwise to be and remain in full force and virtue.”

The court, while recognizing the rule to be the same as "hat adopted by our statute, said:

“We take the rule to be that, to entitle a third person to recover upon a. contract made by others, there must not only be an intent to secure some benefit to such third, person, but the contract must have been made and entered into directly and primarily for his benefit. * * * Applying these rules to the case in hand, it seems clear that plaintiffs cannot maintain this action, because there is no promise by * * * [the guarantors] to pay for labor and material used by Robertson Bros, in the performance of their contract with the city; nor was. the bond taken by the-' city for the benefit of parties who might furnish such labor and material, but to indemnify and save it harmless from loss or damage by the failure of 'Robertson Bros, to perform their contract. * * * The' condition that, if Robertson Bros, should comply with their contract with the city, the obligation should be void, is incorporated in the bond for the benefit of the sureties., It simply declares upon-what terms they may be exonerated from their liability to' -the city. The bond contains no covenant or *119 agreement to pay the plaintiffs, or to see them paid, but only a condition, the performance of which will exonerate them from liability; and such a condition will not be construed as a promise. * * * The condition standing' by itself -wants the very elements of a contract”-— citing Turk v. Ridge, 41 N. Y. 201 , and other New York decisions holding that a condition in a contract of guaranty is not a promise to pay.

The court further said:

“The case of Jordan v. Kavanaugh, 63 Iowa, 152 , 18 N. W. 851 , is, we think, clearly distinguishable from the case at bar in this: That the-contract containing the promise of the principal to pay all just claims of subcontractors is attached to and made a part of the- bond, and the two instruments were considered and read together by the court in determining the undertaking of the obligors * * * to pay such claims.” ■

In the Iowa case the condition of the bond was as follows:

“That, whereas, * * * as principal, has this day entered into a contract with said * * * a copy of which is hereto attached and made a part thereof; now if the said * -* * shall well and truly comply with said contract in the time and manner provided, then this obligation shall be void, otherwise in full force and effect.” This case is in line with Connor v. Olson, 136 Wis. 13 , x 15 N. W. 81 -1. In the latter case the contractor expressly- agreed to furnish, all labor- and- material, and that the school district should not be liable therefor. The condition in the bond was that—

“If J. J. Olson & Son shall duly perform the contract and fulfill all -the several stipulations therein- provided, ‘and pay for all labor and -material that- enter into the construction of said building/ then the obligation to be void,” otherwise to'remain in full force and effect.

The court construed these provisions as an agreement of the contractor to pay for labor and material, and says:

“Since the bond secured' payment by the contractors of the material used in the construction of the building, it was therefore a contract between the district and- the parties thereto for the benefit of those persons furnishing material to be used in the construction of the building. Under such circumstances the third party need not be ascertained or known at its inception to entitle him to the benefits thereof-. The third party -may adopt it *120 when he becomes informed, and may enforce it at la-W' as if originally made by his express authority.'’

These cases hold in effect that, when read in connection with provisions of the contract guaranteed, a condition in a guaranty contract “may” be construed to be a promise; that one of the acts guaranteed may be the payment by the contractor of laborers and materialmen; and that such contract is made expressly for their benefit, as well as for the benefit of other parties named in the contract.

[5,6] The contract between the Offerman Construction Company and the city of Watertown, as pleaded in paragraph 5 of the complaint, contains no express agreement by the construction company to pay for labor and material used in the construction of the sewer, but the bond recites that—

The Offerman. Construction Company has “contracted with the city of Watertown, S. D., to furnish material and labor for and to construct * * * a * * * sanitary sewer * * * known and designated as trunk sewer No. 1, in the contract therefor and plans, specifications, and instructions to 'bidders therefor, hereto attached and specifically made a part of this obligation and referred to herewith; -* * * if the said principal shall well and truly perform all of the terms, conditions and agreements made and entered into by it in said contract * * * and if the said Offerman Construction Co. shall assume the defense of and indemnify and save harmless the city of Watertown, iS. D., its officers and agents, from all claims relating" to labor and materials furnished under said contract * * * and shall hold said city of Watertown, S. D., harmless against all claims for damages whatsoever, arising from injury to persons or property done in the prosecution of the work under said contract; and shall also pay for all labor performed or material used or furnished in the carrying out of said contract;. then this obligation shall be null and void, otherwise to remain in full force and virtue.”

. -These provisions of the bond guarantee that the contractor will do four things: First, construct the sewer according to plans and specifications; second, that the contractors shall assume the defense of and indemnify and save harmless the city of Watertown from all- claims relating to labor and materials furnished under said contract; third; shall hold said city harmless *121 against all claims for 'damag'es whatsoever, arising from -injury to persons or property done in the prosecution of the work under said contract; and, fourth, that the “contractor”' shall pay for all labor performed or material used or furnished in the carrying out of said contract. The first three of these conditions are specificalfy and directly for the benefit and protection of the city. Claims of laborers and materialmen are twice referred to in the provisions,.of the bond: First, in that the city is to be indemnified against such claims; second, that such claims are to be paid. The first of these inures to the exclusive and direct benefit and protection of the city; the second seems to be primarily for the benefit and protection of laborers and materialmen, and only “indirectly” for the 'benefit and protection of the city. Laborers and materialmen, upon complying with the statutes of this state, may acquire a lien upon moneys due or to become due the contfactor for the construction or repair of any work for any county or municipal or public school corporation. ’Section i, c. 133, Laws 1895; section 713, Code of Chdl Procedure ('Rev. Code -1919, § 1660).

In Sioux Falls Pressed Brick Co. v. Board of Education, 25 S. D. 36, 125 N. W. 291 , this court held in effect that, where a contractor had defaulted in the performance of his contract, payment, for a portion of the work completed, which did not become due the contractor until the final completion of the contract, did not become subject to the liens of laborers or material-men under this statute, and that moneys thus retained by and remaining in the hands of the board of education might be used by them in the completion of the contract. This rule was recently affirmed by this court in the case of Grant County v. McGowan Lumber Co., 172 N. W. 683 .

[7] In view of this ruling, it has been suggested upon this appeal that the guaranty contract of defendants may not be construed as a contract made expressly for the benefit of laborers and materialmen, for the reason that the effect of such construction would be to enlarge the liability upon the contract of indemnity intended only to protect the city, which liability extended only to' the amount which might be due the defaulting contractor after completion of the contract by the city itself. If the indemnity contract upon a fair consideration and interpretation of *122 all its terms- and conditions must -be construed as intended for the benefit of the city alone, this objection is insuperable. On the other hand, i-f it appears from- all the terms and express conditions of the bond that it was intended for the protection of both the city and of laborers and materialmen, such an objection is without force. We are inclined to the view that the latter interpretation should be adopted in this case, and that, in view of all its terms, and -conditions, the contract should be construed as having -been made expressly for the protection of laborérs and materialmen as well as the city.

- It follows that the order of the trial court should be affirmed.

Concurrence — Whiting

Text extracted by OCR from a scanned original; check the original for exact wording.

WHITING, J.

(concurring specially). While I concur in the result reached in the foreg'ong opinion, T arrive at my conclusion through a.somewhat different line of reasoning-.

I am unable to agree with the suggestion that this bond may be treated as one entered into between the construction company and the surety company for the benefit of the materialmen. The only contract before us is one wherein the construction corn-pan}’, as principal, and the surety company, as surety, have contracted with the city; the consideration therefor being- the letting of the contract by the city to the construction company. We have therefore a case of-a bond given by a principal and surety upon which a person not a party thereto claims a right of recovery upon the ground that such bond was entered into for its benefit. Suppose the fourth condition was the sole condition of said bond. Such a bond would be in no sense an indemnity bond- — it would not indemnify the city against anything. W”e must presume that the parties to this bond knew that the city could not become liable to the materialmen. The fourth condition does not indemnify the city, but guarantees the payment of the laborers and materialmen. The validity of contracts of guaranty running- in favor of a third party often rests, as held in Fry v. Ausman, 29 S. D. 30, 135 N. W. 708 , 39 H. R. A. (N. S.) 150, Ann. Cas. 19141c, 842, upon the existence of some obligation from the promisee to the beneficiary. It is not, however, necessary that this be an obligation to pay money, or even that it be a legal obligation. A moral obligation from the promisee to the beneficiary or an indirect benefit flowing to the promisee because of *123 s-uch guaranty may be sufficient to create a privity between such promisee and beneficiary. Because of the fact of the existence of a bond with such a condition, a better class of laborers and materialmen will seek to furnish labor and material for public works. The fact that the payment of laborers and materialmen is insured by this guaranty is to the interest of the city wherein such laborers and materialmen live or do business. Such indirect benefits to the city are ample reasons to justify the city- in: requiring this condition and to create a privity of interest between city and the intended beneficiaries. That such a bond is of public benefit is recognized in this and many states by statutes, such as our chapter 245, Laws 1909, requiring public corporations to take such bonds of parties with whom they contract for public buildings, etc.

In taking and giving a bond with such a condition, the parties' thereto understand' that the incidental benefit to be derived by the city,, and which prompts the city to require the condition, comes solely through the guaranty in favor of the material-men and laborer. It must therefore be conclusively presumed that this covenant of guaranty is inserted in the bond for the direct benefit of the materialman and the laborer, in order that through the promise of such direct benefit there will come an incidental benefit to the city.

It does. not appear that the contract between the city and the construction company contained any promise by the construction company to pay laborers and materialmen, and' it i$ contended that the condition contained in the bond cannot 'be held to be a promise on the part of the construction company. To my mind, the sole question to be determined is: What was contemplated by the-parties to this bond when it was entered into — what they intended? It seems clear to me that it was contemplated by the parties that this bond, so far as its fourth condition was concerned, should not be a nullity, but that, by inserting such condition, the construction company and its surety intended to', and the city intended they should, guarantee the payment of the material-man and the laborer, thus bringing an- indirect beenfit to the city. That being their intention, we should not look for excuses to relieve the surety company, but should hold it in strict accord *124 with such evident intention. The rule that sureties are favorites of the law has no application to surety companies. 32 Cyc. 306.

How later courts describe this case

No later court has written an explanatory parenthetical about this case yet.

1926: 11927: 11930: 11931: 11935: 11971: 11999: 12002: 119262026peak 1926 · 1

Relies on it most ⓘ

  1. Carstensen Contracting, Inc. v. Mid-Dakota Rural Water System, Inc.2002 SD 136, 653 N.W.2d 875
  2. Harms v. Northland Ford Dealers1999 SD 143, 602 N.W.2d 58
  3. Thompson Yards, Inc. v. Van Nice239 N.W. 753 (S.D. 1931)
  4. State ex rel. Farmers State Bank v. Kuipers Const. Co.190 N.W.2d 769 (S.D. 1971)
  5. Gary Hay Grain Co., Inc. v. Carlson255 P. 722 (Mont. 1927)
  6. J. F. Anderson Lumber Co. v. National Surety Co.207 N.W. 53 (S.D. 1926)

Most recent

  1. Carstensen Contracting, Inc. v. Mid-Dakota Rural Water System, Inc.2002 SD 136, 653 N.W.2d 875
  2. Harms v. Northland Ford Dealers1999 SD 143, 602 N.W.2d 58
  3. State ex rel. Farmers State Bank v. Kuipers Const. Co.190 N.W.2d 769 (S.D. 1971)
  4. Foster v. Kerr & Houston, Inc.179 A. 297 (Me. 1935)
  5. Thompson Yards, Inc. v. Van Nice239 N.W. 753 (S.D. 1931)
  6. Cove Irr. Dist. v. American Surety Co. of New York42 F.2d 957 (9th Cir. 1930) · Dissent

Citing references are not a citator: they show that a later opinion cites this case, not whether it followed, distinguished, or overruled it. Check negative history before relying on this case.

Authorities cited 12

DepthCaseCited by
Chung Kee v. Davidson, 15 P. 100 (Cal. 1887) 34
Jordan v. Kavanaugh, 18 N.W. 851 (Iowa 1884) 50
Parker v. Jeffery, 37 P. 712 (Or. 1894) 48
Clark v. Howard, 44 N.E. 695 (N.Y. 1896) 27
Elec. Appliance Co. v. United States Fid. & Guar. Co., 85 N.W. 648 (Wis. 1901) 44
R. Connor Co. v. Ætna Indem. Co., 115 N.W. 811 (Wis. 1908) 27
Turk v. Ridge, 41 N.Y. 201 (1869) 26
Fry v. Ausman, 135 N.W. 708 (S.D. 1912) 23
Fish & Hunter Co. v. New England Homestake Co., 130 N.W. 841 (S.D. 1911) 6
Sioux Falls Pressed Brick Co. v. Bd. of Educ., 125 N.W. 291 (S.D. 1910) 4
Fix v. Loranger, 15 N.W. 81 (Mich. 1883) 2
Grant Cnty. v. McGowan Lumber Co., 172 N.W. 683 (S.D. 1919) 1

Keyboard shortcuts

/Focus the search box
j kNext / previous result
EnterOpen the selected result
xAdd / remove the selected result from the download list
n pNext / previous search term in a case
cCopy the citation of the current case
+ −Larger / smaller reading text
?Show this list